Summary
- Uniserve’s 21 October update targets 1 MW of initial operating capacity at VAN-2 in Q4 2026; a second megawatt is described as future expansion.
- Its 2025 lease and build announcement described a 10,000-square-foot facility designed for 2 MW, a C$12 million total budget and a C$6.5 million first phase.
- A filed 2025 MD&A says the 10-year lease began on 1 September 2026 and was with a company controlled by a significant shareholder.
- Public releases do not identify commissioning, utility energisation, activated customer load or a VAN-2-specific customer contract.
The second megawatt did not vanish. It moved into a sentence about the future.
Uniserve’s October update says its VAN-2 data centre in Vancouver is targeting an initial operating capacity of 1 MW in the fourth quarter of 2026. It lists an additional megawatt as available for future expansion. The site is about 10,000 square feet. The company describes a Tier III design, redundant power and cooling, racks supporting up to 30 kW, carrier-neutral connectivity and controlled access as planned capabilities.
That phrasing matters because the project started with a larger headline. In September 2025, Uniserve said it had secured a lease at 369 Terminal Avenue for a facility designed for 2 MW. The initial release put the total budget at C$12 million and estimated the first phase at C$6.5 million. A follow-up said the lease had been signed. The filings describe a ten-year term beginning 1 September 2026.
The public record now gives a phased target: 1 MW for Q4 2026 and another megawatt for a future expansion. It gives no reason for the phase boundary.
The lease creates a calendar with real economics. Uniserve’s interim filing estimated rent at about C$448,000 a year for the first five years and C$478,000 for the next five. It also records a C$1 million lease inducement, a C$1 million forgivable loan tied to warrants and a C$74,610 deposit. The landlord, 369 Terminal Holdings Ltd., was described in the filing as a related company controlled by a significant shareholder. The filing places those terms beside the related-party disclosure.
There is a second set of numbers behind the expansion story. Uniserve reported FY2026 revenue of C$10.19 million, an operating loss of C$2.50 million and a net loss of C$4.70 million. The result included a C$1.95 million impairment loss, while the comparative year was restated for a C$196,700 warrant-valuation adjustment. None of those figures is allocated to VAN-2. They show the company’s reported financial position; they do not reveal the project’s present cash commitments or remaining construction budget.
Uniserve also announced a five-year AI-compute service contract for two servers at a Vancouver data centre in September. The release does not name the site. Putting that contract on VAN-2’s sales ledger would turn an unnamed location into a fact the company has not published.
That leaves a clean test for the new capacity story: one project-specific commissioning record that connects delivered power, installed equipment and activated customer load. Until then, 1 MW is an operating target; the second MW is an expansion option; and neither phrase should be promoted into a completed service.
Sources
- Uniserve, VAN-2 update, 21 October 2026.
- Uniserve, lease and 2 MW plan, 15 September 2025.
- SEDAR+, interim MD&A and financial statements, 31 August 2025.
- Uniserve, FY2026 results.
- Uniserve, five-year compute-services announcement.
Member Briefing
Deeper Profile Context
Sign in with the right membership level to unlock the full briefing and source notes.
Only for Strategic Circle
Strategic Circle
Open to all readers. Unlock profile briefings after joining and signing in.
Join Strategic CircleOnly for Leadership Alliance
Leadership Alliance
For qualified IP-asset owners and management; sign in to unlock alliance briefings.
Join Leadership Alliance