Summary
- Section 2 of the Digital Infrastructure Act 2026, published on 10 November 2026, defines critical IT load as the maximum electrical power a data centre is designed to supply to its hosted IT and network equipment; section 26(2) makes that figure a term of the licence an operator must hold.
- The Data Centre – Call for Application provisionally allocated 200MW in August 2026, 50MW each to four named operators, without ever defining its megawatt or mentioning critical IT load.
- Keppel, one of the four, prints about 900MW of "gross power capacity" at end-September 2026 including projects under development, 60 per cent operational — a third quantity on a third perimeter, with no printed conversion to either of the other two.
Singapore does not sell data-centre capacity; it allocates it. On 7 October 2026 Parliament passed the Digital Infrastructure Bill, the President assented on 29 October, and on 10 November the Digital Infrastructure Act 2026 was published in the Acts Supplement as No. 25 of 2026 (Digital Infrastructure Act 2026). Section 2 of that Act defines the unit in which the country's scarcest digital input is now licensed. Section 26(2) makes the defined figure a licence term. The exercise that hands out the megawatts writes "200 megawatts of new capacity" and "50MW" four times without ever saying which megawatt it is handing over.
What the statute put a number under
"Critical IT load", in relation to a data centre, means the maximum electrical power capacity for which the data centre is designed to supply electrical power to any information technology and network telecommunications equipment (including computer servers) that provide storage, processing and transport of data, and that are hosted within the data centre. That is the enacted wording, and it is the only explicit definition of a data-centre megawatt Singapore has written into law.
The same section defines a data centre as a facility carrying a critical IT load of 3 megawatts or more, and section 26(2) requires a DC licence to specify the critical IT load at which the data centre may be operated.
The ministerial explanation is blunter than the statute. At the second reading on 6 October 2026, Senior Minister of State for Digital Development and Information Tan Kiat How put it this way: CIL is the "rated size" of the data centre's computing power supply — the maximum electrical power it is designed to deliver to its servers and other IT and network telecommunications equipment it houses. "To be clear," he added, "it is not the amount of electricity the data centre consumes at every moment" (MDDI second reading speech). The same speech puts the major data centre facility services regime at 10MW of critical IT load and the sustainability licensing regime at 3MW, whether the operator serves third parties or uses the facility itself. The Schedule paragraph carrying the 10MW threshold was not visible in the Act text I could read; the ministerial speech is what carries it here.
Two more instruments belong beside those. Bill No. 20/2026 was read the first time on 8 September 2026 with the same clause numbering (Bill No. 20/2026). Publication is not commencement: the Act comes into operation on a date appointed by the Minister, and that date is not established by the text I read. Baker McKenzie's October 2026 note reads the licensing regime as the hook that will make strategic, economic and green-energy commitments given in exchange for new capacity, such as through the DC-CFA, enforceable as licence conditions — and records that each licence will specify the critical IT load at which the facility may operate (Baker McKenzie). Channel NewsAsia's report of the 7 October passage, after a second reading debate of more than five hours across two days, records the 3MW licensing threshold, the 10MW regime for major co-location and cloud facilities, and a maximum penalty of S$1 million or 10 per cent of the licensee's Singapore turnover, whichever is higher (Channel NewsAsia).
The allocation never uses the word
The DC-CFA2 launch factsheet of 1 December 2025 sizes the round: "At least 200MW of DC capacity will be made available, with potentially more through the adoption of new and innovative green energy pathways." It calls the DC-CFA the primary mechanism for DC capacity allocation, and it defines its efficiency test to the second decimal — PUE of 1.25 at 100 per cent IT load or better, with a footnote explaining that PUE is a ratio of total annual DC energy utilised over total annual IT equipment energy utilised (DC-CFA2 launch factsheet). Read end to end, the factsheet does not define what the 200MW measures, and prints no land area, floor area or electrical connection beside it.
The award factsheet of 21 August 2026 is specific about recipients and no more specific about the unit. EDB and IMDA "provisionally allocated 200 megawatts of new capacity" to four operators — 50MW each to Digital Realty, Equinix, Keppel Data Centres and ST Telemedia Global Data Centres, listed alphabetically — after more than 20 proposals. Facilities will be on Jurong Island; awardees must obtain at least 50 per cent green energy and BCA-IMDA Green Mark for Data Centres 2024 Platinum (DC-CFA2 award factsheet). Names, not projects. No per-company land area, floor area, grid connection or contracted capacity. And no sentence saying whether each 50MW is IT load, facility load, contracted capacity or design capacity; the phrase "critical IT load" does not appear.
"Provisionally allocated" is the award's own phrase, and it describes a permission to develop, not a delivered load. Nothing in the reviewed set says the 200MW is commissioned, built, energised or consumed.
The pilot is the precedent and repeats the pattern. The 2022 annex sets PUE at 1.3 at 100 per cent IT load on the same annual-energy definition, and prints no megawatt pool, no per-applicant cap and no land term (2022 pilot annex). EDB's July 2022 article says there is no limit on the number of applicants accepted "but the total capacity allocated is expected be around 60MW" — an expectation, printed as one (EDB pilot launch). In July 2023 the same two agencies provisionally awarded "about 80 MW" to AirTrunk-ByteDance (Consortium), Equinix, GDS and Microsoft, with no per-company split and no unit defined (2023 pilot award). The 60MW was never a cap and the 80MW did not breach it; the page had already said there was no limit on applicants.
One reviewed government page puts land and megawatts on the same line, and it does so at park level: about 20 hectares on Jurong Island reserved for the low-carbon data centre park, land "able to provide up to 700MW of power capacity for the facilities" (Jurong Island park). The May 2024 Green Data Centre Roadmap aims at "at least 300 megawatts (MW) of additional capacity in the near term, with potentially another 200MW and more", and puts Singapore's total data-centre capacity above 1.4GW — again without saying what the megawatt is (Green Data Centre Roadmap).
Commentary fills the gap from outside, and none of it binds the instrument. Norton Rose Fulbright's August 2026 analysis records that the DC-CFA2 application window closed on 31 March 2026 and glosses "100 per cent IT load" as "fully designed computing capacity"; it also calls Jurong Island a prime site rather than the only permitted location, which sits awkwardly against the award factsheet's plain statement that supported facilities will locate there (Norton Rose Fulbright). An ICAM sector report published through SGX on 26 March 2026 states the industry's working equivalence — "MW or IT load refers to power delivered to IT equipment" — and separates megawatts from racks, cabinets, white space and floor area (ICAM sector report). Useful, unauthoritative, and not the awarding page.
The recipient prints a third number
Keppel Ltd's 3Q and 9M 2026 business update, dated 29 October 2026, states that the portfolio spans 39 data centres with a gross power capacity of about 900MW as at end-September 2026, that 60 per cent of that gross power capacity is operational, and that the group was awarded 50MW of new data centre capacity under DC-CFA2 (Keppel 3Q 2026). The same panel prints attributable lettable area of 2,872,251 sq ft across 27 assets and 2,022,800 sq ft across 12 Keppel and private-fund assets, with no tie to the megawatts. The glossary defines the portfolio's gross power capacity with one clause: it includes projects under development.
The 1H 2026 presentation of 30 July 2026 states 37 data centres at 840MW of gross power capacity as at end-June 2026, 60 per cent operational, off the same glossary line (Keppel 1H 2026). The Annual Report 2025 connectivity review states more than 800MW in 39 data centres, including projects under development, and prints discrete project figures: a 25MW floating data centre, and a 720MW powerbank near Melbourne secured in January 2026 for the potential deployment of an AI data centre campus on a 123-hectare contiguous site (Keppel Annual Report 2025).
Then there is the 50MW itself. Keppel's 21 August 2026 announcement attaches it to a named facility — Keppel Data Centre Singapore 11, an AI-ready data centre on Jurong Island — with expected investment of more than S$1 billion, funded by Keppel Data Centre Fund III and co-investors, targeting a PUE of under 1.2 with more than 50 per cent of power from eligible green energy pathways (Keppel 50MW announcement). The announcement characterises the 50MW in no unit: not IT load, not gross or facility power, not contracted capacity, not design capacity. It prints no as-at date other than the award date, and no floor area or land area beside the 50MW. The PUE is a forward-looking design ambition published without a numerator, a denominator, a measurement boundary or a method.
The REIT that owns part of this estate prints power as a proportion and never as megawatts. Keppel DC REIT's Investor Day 2026 presentation records contracted power capacity of about 96 per cent as at 30 September 2026 — about 97 per cent including Tokyo Data Centre 4 and 5 — with a footnote defining the metric as the proportion of revenue-generating power capacity, across 27 data centres in 10 countries and assets under management of about S$7.6 billion (Keppel DC REIT Investor Day 2026). Its per-asset tables give attributable lettable area in square feet beside occupancy, weighted average lease expiry and land-lease tenor. No megawatt total appears in the portfolio metrics.
Its Sustainability Report 2025 defines PUE only as "a ratio that describes how efficiently a data centre uses energy", and reports performance as a 12.1 per cent reduction in "effective PUE" against a 2019 baseline for fully-fitted colocation assets that underwent major asset enhancement, with DNV assuring achievement of the target (Keppel DC REIT Sustainability Report 2025). It publishes total energy consumption of 2,053,859 GJ with a landlord and client split, and defines energy intensity on total energy consumption divided by total gross floor area in square metres. Those are the components from which an energy ratio could be built. They are not presented as a PUE, and they are not tied to any megawatt.
Four quantities on four perimeters
Line the numbers up with what each one counts. Singapore's total data-centre capacity of more than 1.4GW: national, May 2024, installed and planned. 200MW provisionally allocated: four operators, 21 August 2026, a grant. Up to 700MW of power capacity for about 20 hectares: a land envelope, October 2025. About 900MW of gross power capacity including projects under development: one listed group's portfolio, 30 September 2026. Four quantities, four dates, four perimeters — and a share of one in another is not a finding.
200MW is not 14 per cent of 1.4GW, and Keppel's 50MW is not 5.6 per cent of its portfolio, because the numerator is a provisional grant of unbuilt capacity and the denominator is a design figure that already contains unbuilt projects.
The arithmetic that does hold is thin, and it is mine. 50MW × 4 = 200MW, which is the award factsheet's own sum. About 900MW minus 840MW is about 60MW of gross power capacity added between end-June and end-September 2026, while the printed asset count moves from 37 to 39 — and no reviewed text reconciles either number, so rounding, a change of perimeter or a genuine addition could all explain the gap. Sixty per cent of about 900MW is about 540MW stated to be operational and about 360MW not operational.
And the quarter's entire increase in this portfolio's gross power capacity is of the same order as a single 50MW award to the same group: a state allocation to a facility not yet built and a portfolio-wide design total are two different measuring acts, and the fact that they are similar in size is a coincidence of units, not a comparison.
Two quotients get printed here only to be refused. 720MW ÷ 123 hectares is about 5.9MW per hectare, but the numerator is a powerbank — rights to lease power near Melbourne — and the denominator is a contiguous site, so the quotient is not a built density and describes no facility. And nothing at all follows arithmetically from "about 96 per cent contracted power capacity", because the base it is a proportion of is a phrase, revenue-generating power capacity, printed without a number.
The ratio closes to two decimals; the megawatt to none
Set the efficiency test beside the capacity number and the asymmetry is the story. PUE has a two-decimal threshold, a defined numerator and denominator, a stated load condition and a footnote on every factsheet. The megawatt has a statute-book definition, a licence term and four awards — and no reviewed document joins them. Nothing states that the section 2 definition governs the megawatt allocated under the DC-CFA. Nothing states that it does not. The law-firm reading links the two only through licence conditions, and a cross-reference buried in an application annex I did not see is not excluded.
Nor is there a measured ratio anywhere in the set. PUE appears as a requirement (1.3 in 2022, 1.25 in 2025), as a design target (under 1.2 for Keppel DC SGP 11) and as a percentage reduction in "effective PUE" (12.1 per cent). No reviewed page prints the numerator and denominator of a PUE actually measured for a named Singapore facility; the closest arithmetic is the sustainability report's energy total over gross floor area, which is an energy intensity. The series that would sit between a required ceiling and a reported outcome does not exist in what I read.
My own 13 November 2026 briefing on this round read the 1.25 requirement as a design standard and asked what the ratio measures and who checks it. That piece took the megawatt as given. Six weeks later the ground under the unit moved, and this one takes the megawatt itself.
What this does and does not say
- Every absence here is a count over the documents listed below, read on 24 November 2026, and nothing more. Several were read as retrieved PDF or page text that may be truncated.
- Publication of the Act is not its commencement; the appointed date is not established by the reviewed text.
- "Provisionally allocated" is a permission to develop, not a delivered load.
- The 50MW lots are per operator, not per project; the award does not divide them among facilities, and the operator attaches one named facility to the whole of its lot.
- Keppel's three portfolio printings — more than 800MW in 39, 840MW in 37, about 900MW in 39 — are reproduced and none is adopted.
- Three counted objects stay three: an awarded megawatt, a statutory critical IT load, and a gross power capacity that includes projects under development.
The documents
- EDB and IMDA, DC-CFA2 launch factsheet, 1 December 2025
- EDB and IMDA, DC-CFA2 award factsheet, 21 August 2026
- IMDA and EDB, Annex A: Summary of Pilot DC-CFA Key Parameters and Criteria, July 2022
- EDB, Singapore pilots sustainable way to grow data centre capacity, 20 July 2022
- IMDA and EDB, pilot DC-CFA award, 14 July 2023
- EDB, Jurong Island low-carbon data centre park announcement, October 2025
- Digital Infrastructure Act 2026 (No. 25 of 2026), published 10 November 2026
- MDDI, Second Reading speech by Senior Minister of State Tan Kiat How, 6 October 2026
- Digital Infrastructure Bill No. 20/2026, 8 September 2026
- Baker McKenzie, Singapore: Parliament Passes Digital Infrastructure Bill, October 2026
- Channel NewsAsia, report on the data centre regulations, 7 October 2026
- IMDA, Green Data Centre Roadmap, May 2024
- Norton Rose Fulbright, Singapore's Green Data Centre Roadmap and DC-CFA2, August 2026
- ICAM, Singapore's Data Centres sector report, 26 March 2026
- Keppel Ltd, 3Q and 9M 2026 business update, 29 October 2026
- Keppel Ltd, 1H 2026 results presentation, 30 July 2026
- Keppel Ltd, Annual Report 2025 connectivity review
- Keppel Ltd, announcement of the 50MW award, 21 August 2026
- Keppel DC REIT, Investor Day 2026 presentation, 12 November 2026
- Keppel DC REIT, Sustainability Report 2025, March 2026
The point
Singapore has done the harder thing. It wrote down what a data-centre megawatt means, made that meaning a licence term, and set thresholds at 3MW and 10MW that only work if the number is the rated design maximum. It has not yet carried the definition into the queue through which the capacity is actually granted.
Until a single page prints the definition, the allocation and the as-built figure together, the word keeps doing the work of the number — and the safest reading of any Singapore data-centre megawatt is that it describes what the facility is designed to deliver: not what it consumes, not what is built, and not necessarily what was granted.
Member Briefing
Read the full trend briefing
Members read the full briefing with the source notes behind every finding.
Strategic Circle
A daily briefing in your language, built from changes we have verified.
Join for USD 20/monthCancel anytime.
Members also get the full research library, a daily briefing on the networks they follow and the private forum.