Summary

  • Ireland's data-centre load is written three times by three offices in three units: maximum import capacity in MVA in the connection agreement, demand in MW in the adequacy assessment, metered consumption in GWh at the statistics office.
  • Peak data-centre demand to date is about 800 MW on the operator's own printing. The 2025 metered total is 7,663 GWh, which across 8,760 hours averages 875 MW.
  • The contracted ceiling is 2,400 MVA against a modelled 2024 demand of 959 MVA for the same bundled category, and the contracted project count moved from sixteen to seventeen while a full year printed 0.0 MVA of newly executed demand agreements.

The unit lives in the contract

The binding number in an Irish data-centre connection is called maximum import capacity. EirGrid's 2020 connection policy defines it as "the maximum amount of energy stated in MVA that the customer wishes to import from the transmission system at any point in time", and adds that it is "a single number, i.e. not a range" (Data Centre Connection Offer Process and Policy, version 2).

The operator's current guidance drops the unit. Maximum import capacity is "the maximum amount of capacity or quantity of power which is proposed to be used", and exceeding the contracted figure triggers an Unauthorised Usage Charge (Demand Connections). Two sentences, one company, five years apart: the older names megavolt-amperes and calls the quantity energy, which it is not; the newer names no unit at all. Neither is wrong enough to trouble an engineer. Both leave a reader without the unit that the regulator, six months after the second sentence was posted, uses as a legal threshold.

What the operator prints, and where the units part

The clearest connected-capacity statement in the reviewed set is the November 2025 information paper on large-demand fault ride-through. "The peak data centre demand to date is approximately 800 MW; approximately 650 MW connected on the transmission system and 150 MW on the distribution system" (Large Demand Facility Fault Ride Through, November 2025). The same paper confesses the seam: it uses MW rather than MVA "for simplicity" and warns that the MW values may differ slightly from the MVA equivalents in connection agreements and capacity statements.

The adequacy assessment keeps the contract's unit. It prints "approximately 2,100 MVA of demand capacity that is contracted to data centres and other new technology loads at the transmission level, and approximately a further 300 MVA contracted at the 110 kV distribution level", covering seventeen transmission-level projects and five at 110 kV that are either connected or hold a signed agreement (All-Island Resource Adequacy Assessment 2026-2035). Its predecessor counted sixteen projects and the same 2,000 plus 300 MVA (Generation Capacity Statement 2023-2032). Then the ceiling changes alphabet: "Ireland has 2 GW of contracted data centres mostly located in the greater Dublin area", nearly a third of entire Irish demand at full utilisation, with a further 6 GW of expressed interest (Data Centre Constrained Area Overview, May 2026).

The 2 GW and the 2,400 MVA overlap and are not the same quantity printed twice. One is a rounded gigawatt statement, the other a megavolt-ampere contract total, and no reviewed page states the power factor that would join them. This article does not assume one, and so it does not convert. The same discipline applies to the system peak: 7,502 MW all-island on 8 January 2025, of which 6,024 MW in Ireland and 1,498 MW in Northern Ireland, against a minimum of 3,095 MW on 9 June 2024 (adequacy assessment, above), while the 2024 performance report prints a calendar-year peak of 7,148 MW on 27 November 2024 at 17:26 (All-Island Transmission System Performance Report 2024). Two peaks, two windows, both correct.

MPID 345 is the one reviewed page that puts a data-centre number beside a peak number in one breath: "current data centre demand can therefore make up approximately 11% of peak demand or 26% of minimum demand", with data centres and new technology loads at about 24% of Ireland's electrical energy requirements in 2024 (MPID 345). An 11% share of peak is a share of an instant; a 24% share of energy is a share of a year. They are two claims wearing one subject.

Multiply those two shares back into their denominators and they land on the operator's own figure. Eleven per cent of the 7,502 MW all-island peak is about 825 MW; 26 per cent of the 3,095 MW minimum is about 805 MW. Both multiplications are mine, and both denominators are the peak and minimum printed in the 2026-2035 assessment read here, one edition later than the one MPID 345 cites, so this is an order-of-magnitude check rather than a same-edition comparison. What it shows is that the megawatt surfaces agree with each other to within a few per cent. The disagreement is not among them. It is between all of them and the meter.

The two figures that cannot both hold

The statistics office measures the year. Metered electricity consumption by data centres rose from 6,973 GWh in 2024 to 7,663 GWh in 2025, a 10% increase, and reached 23% of total metered electricity against 5% in 2015 (Data Centres Metered Electricity Consumption 2025).

Divide 7,663 GWh by the 8,760 hours in a year and the data centres drew 874.8 MW as a year-round average. The division is mine; the two operands are theirs. A peak cannot be smaller than the average of the days inside its own window, and the operator's "to date" window ends in November 2025, inside the year the meter covers. Set the printed 800 MW against the printed 7,663 GWh and the peak is under the average it is supposed to bound. Reverse the multiplication: 800 MW held for every hour of the year yields 7,008 GWh, which is 655 GWh short of what the meter recorded, about 8.5% of the total.

Something is being counted twice or counted differently, and nobody publishes which. The candidate explanations are all plausible and all unprinted. The perimeters may differ: the operator's figure is a connection register's demand, the statistics office's is a metered class. The windows differ by a month at the tail of a growing load. And a figure described as "peak demand to date" does not say whether it is a metered peak, a modelled connected load, or nameplate capacity in use. What is not available is the sentence that would settle it, and that sentence belongs to neither office.

The regulator's own summary supplies a third number for the same year. With currently contracted demand, it cites an EirGrid forecast that data-centre electricity demand rises from 9.4 TWh in 2025 to 14.6 TWh in 2034 (CRU news release, 12 December 2025). Divide 9,400 GWh by 7,663 GWh and the forecast for 2025 sits 22.7% above the metered outturn for that same year; as load, 9,400 GWh across 8,760 hours is 1,073 MW against the metered 874.8 MW. That is a different comparison from peak against average — forecast against measurement — and it is the one printed the right way round: the forecast is the larger number.

Where the numbers do agree is what makes the disagreement interesting. 650 MW plus 150 MW is exactly 800 MW: the operator's own components close against its own total. The gap is not inside EirGrid's paragraph. It opens between that paragraph and the meter.

A ceiling two and a half times the demand it bounds

The adequacy assessment models demand for its bundled category at 959 MVA in 2024, rising to 1,402 MVA low, 1,870 MVA median or 2,183 MVA high by 2035. Set the 2,400 MVA contracted against the 959 MVA modelled and the permit ceiling is 2.50 times the demand the same document expects the category to actually take. That 2.50 is mine. It says the scarce thing in Ireland is not energy and not even capacity. It is permission.

The queue that printed zero and the count that moved by one

"No new demand connection agreements were executed in 2024 (0.0 MVA)", the performance report states, in the same year that 43 generation agreements totalling 3,774 MW and one autoproducer at 288 MW were executed. A zero in a flow column sits beside a stock that barely moves: sixteen transmission-level projects in January 2024, seventeen in February 2026, and seventeen again in September 2026 testimony. The count is a stock of signed agreements, so a year with no new signatures does not reduce it. Sixteen, seventeen, seventeen is what a closed door looks like when the queue behind it was already inside.

The policy written in the meantime is expressed in the contract's unit. The December 2025 large energy user decision sets a de minimis of 1 MVA of maximum import capacity applied to the size of the whole project; between 1 and 10 MVA an autoproducer must meet 100% of the site's maximum import capacity on a de-rated basis; at 10 MVA or more, dispatchable onsite or proximate generation or storage must at minimum match the ramped or enduring maximum import capacity, separately connected and metered and participating in the wholesale market (CRU/2025236, full text). The regulator's own summary adds that at least 80% of annual demand must come from additional Irish renewable generation on a six-year glide path, and that the system operators must publish a data-centre engagement and connection process by 31 March 2026 (CRU news release, 12 December 2025). The 1 MVA and 10 MVA figures are read from a full-text copy of that decision, because the publisher's own file returned no readable text to this reading and is cited as unread below.

The testimony splits the voltage levels

At the Joint Committee on Artificial Intelligence on 29 September 2026, EirGrid's witness counted fourteen data-centre campuses connected directly to the transmission system, three more contracted but not connected, around 1 GW connected against around 2 GW contracted overall. ESB Networks' witness counted 33 data centres connected at distribution level, "approximately 427 MVA of connected capacity, with a further additional 10 MVA" contracted (Joint Committee on Artificial Intelligence, 29 September 2026). Note the unit change between two answers given minutes apart: gigawatts at transmission, megavolt-amperes at distribution. The two are never added, on that page or any page in the reviewed set, so Ireland has no published connected total for its data centres in any single unit.

Three shares and one class

For one class of customer the reviewed set prints 23% of metered electricity in 2025, 22% of national electricity demand in 2024, about 24% of electrical energy requirements in 2024, 11% of peak demand and 26% of minimum demand. Five shares, three definitions, three years. A reader who takes the largest gets a different country from a reader who takes the smallest, and both are quoting the Irish state correctly.

What a reader is actually deciding

A tenant signs megavolt-amperes at a point of connection, pays a network capacity charge on that number, and must now bring generation sized to match it. A lender underwrites that number for the life of the agreement. A regulator administers a 2 GW threshold written in gigawatts against a register kept in megavolt-amperes. A county council reads a national figure in gigawatt hours. Four decisions, one resource, and the conversion between them is nobody's published deliverable. Until it is, the useful question is not how many megawatts of data centres Ireland has.

It is which megawatt, at which point of connection, at which instant, counted against which register, over which period.

Boundaries

  1. Thirteen documents are cited and were read on 25 November 2026; each claim is dated to the document that printed it, not to the day it was read.
  2. The CRU's own decision PDF returned HTTP 403 at this reading, so the operative 1 MVA and 10 MVA thresholds rest on a full-text copy of that decision and on the regulator's summary page. The publisher's file is linked, and labelled unread, in the source list.
  3. Reading grades differ inside the set: four documents were read as full text — three as full page text, one as the full text of a mirror — seven as page or section text returned for their exact URLs without paging the whole document, and one as transcript text that also appeared on a prelive host.
  4. The statistics office's release prints 07 July 2025 in its masthead and 07 July 2026 in its body. The article uses its data and does not silently choose between its dates.
  5. No reviewed page converts MVA to MW. The two units are printed side by side, no power factor appears in any of the thirteen documents, and none is assumed here.
  6. The bundled category "data centres and other new technology loads" is broader than data centres alone, and every MVA figure from the adequacy assessment, the 2023-2032 statement and MPID 345 carries that scope.
  7. The 800 MW, 650 MW and 150 MW figures are printed as "to date" in a paper dated November 2025 with no freeze date. They are quoted as a November 2025 printing.
  8. An absence recorded here is a count over these thirteen documents read on 25 November 2026, not a claim that a figure is unpublished anywhere.
  9. Every quotient and multiple in this article is labelled mine where it appears. No quotient is taken across two perimeters, two voltage levels or two units without saying so.

Sources