- Governor Greg Abbott says fewer than 10% of data-centre companies responded to a Texas request for information needed to assess future electricity demand
- ERCOT is auditing roughly 250–300 projects — about 200GW of potential load — through Batch Zero before they can advance in the grid-connection process
- The wider interconnection queue carries more than 474GW of proposed load, about 90% of it data centres
The fact: 474GW of proposed load, and fewer than one in ten willing to explain it
Texas Governor Greg Abbott said fewer than 10% of data-centre companies responded to a state request for information needed to assess future electricity demand. The number landed after Abbott ordered the Public Utility Commission of Texas and the Electric Reliability Council of Texas to verify projects seeking grid connections before letting them move forward — a demand that developers prove their load is real before the state plans a transmission system around it.
ERCOT is tracking more than 474GW of proposed load in its interconnection queue, roughly 90% of it data centres. The audit's first pass, run through ERCOT's Batch Zero process, covers about 250–300 projects representing some 200GW of potential demand. Reviewers want electricity and water requirements, project ownership, tax incentives, and the measures developers claim will limit the strain on nearby communities. Much of the wider queue is never expected to break ground at all.
The assessment: a queue entry is not a running network
Every interconnection queue in North America now reads like a wish list written by people who may not be in the room when the bill arrives. A 474GW figure is not a forecast; it is an accumulation of intentions — some backed by land, capital and signed customers, many backed by a spreadsheet and an option on a substation. Grid planners cannot size transformers, feeders or generation around intentions.
That is what makes Abbott's disclosure more than a statistic. Fewer than one in ten developers could, or would, answer a straightforward question about how much power they expect to draw. The audit is not an attack on data centres; it is the minimum due diligence any operator would demand of a counterparty before signing a decade-long capacity commitment. Batch Zero forces the paperwork to catch up with the press release: enough detail for ERCOT and the PUCT to judge whether a project is ready to advance, or whether it should quietly leave the line.
The useful number is not 474GW. It is whatever survives. If verification cuts the proposed load sharply, Texas gets a demand picture it can actually plan around — and the projects that remain get a clearer, faster path through studies no longer clogged by speculative placeholders. A queue that mixes running capital with wishful thinking serves neither.
What to watch: how much of the 200GW is still standing
Watch how many of the roughly 250–300 Batch Zero projects clear the audit, and how much of their estimated 200GW remains in the process afterwards. A revised ERCOT demand forecast, confirmed connection studies, and a visible list of projects removed from the queue will show whether verification is a filter or a genuine reset. The headline 474GW will tell you far less than the capacity that survives contact with a question.
Member Briefing
Read the full trend briefing
Members read the full briefing with the source notes behind every finding.
Strategic Circle
A daily briefing in your language, built from changes we have verified.
Join for USD 20/monthCancel anytime.
Members also get the full research library, a daily briefing on the networks they follow and the private forum.