Summary
- Schedule PLL-18 prints a minimum billing demand as a formula in kilowatts — the highest 30-minute measurement over the current month and the preceding eleven, ratcheted, floored at the greatest of the contract minimum, 50 per cent of contract capacity, or 500 kW — and that schedule is closed to any customer of 100 MW or more that did not contract before 1 February 2025.
- Schedule TOU-SC-16, which takes new and existing customers at 100 MW and above, prints no demand formula: the floor becomes a customer-specific monthly access charge that cannot be lowered except by Commission action, and the amounts payable on termination live in a Contract for Electric Service that, for the 3,210 MW contract on the record, was filed as a trade secret in its entirety.
- The only public exit instrument is a portfolio residual — a revenue deficiency defined across all large-load data centre customers, reduced by termination payments and by named mitigation, with a commitment not to recover it from customers below 100 MW.
The schedule that prints the floor is the one a new large load cannot use
Schedule PLL-18 covers customers at 500 kW and over and is effective with bills rendered for April 2025. Its billing demand is the highest 30-minute kW measurement during the current month and the preceding eleven months, with seasonal ratchets at 95 per cent of the prior summer peak and 60 per cent of the prior winter peak. Then comes the sentence that makes the schedule auditable:
In no case shall the Billing Demand be less than the greatest of: (1) The contract minimum, or (2) Fifty percent (50%) of the total contract capacity, or (3) 500 kW.
That is Schedule PLL-18. Its term of contract is five years and it prints no exit or transition-charge formula; it refers the reader to the Rules and Regulations and to Commission-approved riders, which I did not inspect.
The same schedule is closed. A customer with expected peak demand of 100 MW or greater may take service under PLL-18 only if it contracted before 1 February 2025. Every data-centre load Georgia has signed since then sits on the other side of that line.
The schedule that takes those loads prints a delegation
Schedule TOU-SC-16 applies to new or existing customers with an expected total peak demand of 100 MW or greater on one tract or contiguous tracts of land. The retrieved copy is Original, page 6.10, effective with bills rendered for the billing month of June 2026 (Schedule TOU-SC-16). It prints no demand measurement, no twelve-month window, no ratchet and no greatest-of floor.
What it prints instead is a price mechanism. Under the Monthly Access Charge option the access charge is customer-specific, based on the cost to serve that customer's load and location, may not be lowered except by Commission action, and may be increased to cover added investment. If the Contract for Electric Service does not contain a specific minimum monthly bill, the minimum bill is that access charge plus Environmental Compliance Cost Recovery, the demand-side management schedule, the municipal franchise fee and the administrative charge.
The exit is delegated in one sentence:
The CES will specify the amounts the customer must pay in the event of termination, whether by default or otherwise.
The schedule's term of contract is three years, or as specified in that contract, and its Standard Price Option is unavailable to customers at 100 MW or greater that did not contract before 1 February 2025. A notice period for leaving is printed nowhere in it.
The rulebook permits a floor and quantifies none of it
Underneath both schedules sits paragraph 1 of Section A:
Anything herein notwithstanding to the contrary, the Company may require additional terms and conditions of electric service, including, without limitation, minimum billing requirements and a longer term of contract, when the Company deems it appropriate to ensure the Company recovers all costs associated with serving or preparing to serve a customer with an expected peak demand of 100 MW or greater at one or more premises located on one tract or contiguous tracts of land.
That is the Rules, Regulations and Rate Schedules for Electric Service. The paragraph permits; it states no minimum billing amount, no minimum percentage of contract capacity and no fixed contract length, leaving all three to the individual contract. Section D, paragraphs 13 and 14, added on the same 1 February 2025 revision date, deal with performance and credit provisions and with a 100 MW-or-larger customer's liability on termination for costs incurred in serving or preparing to serve it, including distribution, transmission and generation costs. The general default term is one year, renewed term to term on at least thirty days' written notice — the only notice interval in the general rules, and not a large-load term.
One contract, filed as a trade secret in its entirety
Georgia Power's filing letter of 27 August 2026 records a 3,210 MW contract submitted for Staff review on 27 July 2026 and deemed approved on 26 August 2026, and says of it:
Given the sensitive nature of the contractual terms and conditions, and the competitive information contained therein, all of which is governed by a nondisclosure agreement and confidentiality obligations, the contract is being filed as trade secret in its entirety.
That is the filing letter. A cover letter dated 8 September 2026 then encloses "a public summary of the seventh large load contract for 3,210 MW of electric service" (cover letter). The summary sits inside a zip attachment I did not open, so nothing here states that contract's term, minimum bill, notice period, termination amount or security requirement.
The only public exit figure is a portfolio
The Joint Statement of 26 August 2026 defines the term the docket uses:
For purposes of this provision, “Incremental Cost Revenue Deficiency” is defined as the amount, if any, by which the total forecasted incremental cost for all Large Load Data Center Customers (including Large Load Data Center Customers that have terminated in part or in full) exceeds the total of all Large Load Data Center Customers’ actual and forecasted revenues over the initial term of the contracts.
That is the Joint Statement. The deficiency is reduced by termination payments collected or owed, by the Company's mitigation activities — remarketing of capacity, avoided generation capacity, avoided transmission, retirements and replacement customer loads — and by net benefits attributable to those customers over their initial terms; every mitigation item is named without a value. Georgia Power commits not to seek recovery of any deficiency from customers below 100 MW, and the Commission keeps discretion over any unmitigated remainder, including allocation to other large-load customers. The Company will notify the Commission within 15 days of receiving a termination notice, and will track large-load revenue, the associated minimum bills, and the forecasted revenue requirements on which those minimum bills were based. The statement records that Staff had reviewed six prior large-load contracts and calls the Commission's 28 January 2025 and 17 April 2025 orders its Large Load Contract Review Process Orders.
Three term statements, and no conversion between them
PLL-18 prints five years. TOU-SC-16 prints three years or as the contract specifies. The Commission's news release of 23 January 2025 prints: "The new rule also allows for longer contract lengths (from 5-year contracts to 15-year contracts) and minimum billing requirements for high-load customers." That is a press description, and no tariff schedule in the set prints a fifteen-year term.
The document-index pages for the two orders (filing 221165, filing 222325) confirm their titles, dates and attachments; the attached order PDFs were not opened, so no ordering language is quoted. The Commission's Data Center Fact Sheet of September 2026 states the purpose in its own words: "The rule allows for minimum billing requirements and longer contract terms for new large-load customers. The purpose for the new rule is to ensure data centers continue paying for new infrastructure even if they leave the state." (fact sheet).
Where a reader's arithmetic has to stop
Four observations are mine, not the record's.
One: the floor formula appears on one of the two schedules read and on the other not at all, and the one that prints it is the one a 100 MW-or-larger customer can no longer sign.
Two: 50 per cent of 3,210 MW is 1,605 MW. That multiplication holds only if a 3,210 MW customer were served under PLL-18, only if its total contract capacity equalled 3,210 MW, and only if 50 per cent of capacity were the greatest of the three floor terms. It is not that customer's bill; the record supplies neither its contract minimum nor its contract capacity.
Three: a window of the current month plus the preceding eleven is a rolling twelve months of 30-minute measurements, so one high half-hour carries into eleven later bills unless a ratchet or the contract minimum lifts the floor further.
Four: the Incremental Cost Revenue Deficiency aggregates forecasted incremental cost across all large-load data center customers, so no individual customer's exit price can be solved from it however completely its inputs were printed.
Across the ten documents read, no notice period for a large-load customer is printed. The only notice interval anywhere in the set is the general rules' thirty days before the expiry of a renewed one-year term.
The record, and its edges
- This article reads ten documents on 21 November 2026: the Rules, Regulations and Rate Schedules for Electric Service; Schedules PLL-18 and TOU-SC-16; the Joint Statement of 26 August 2026; the trade-secret filing letter of 27 August 2026; the cover letter of 8 September 2026; the Commission's document-index pages for filings 221165 and 222325; the Commission's news release of 23 January 2025; and the Data Center Fact Sheet of September 2026. No other document is quoted.
- The order PDFs attached to filings 221165 and 222325 were not opened. Only their document-index metadata was read, so no ordering language, condition or effective-date sentence from either order appears here.
- The public summary of the seventh large-load contract sits in a zip attachment I did not open. Nothing here states that contract's term, minimum bill, notice period, termination amount or security requirement.
- The executed 3,210 MW contract was filed as a trade secret in its entirety. Every statement about a 100 MW-or-larger customer's obligations here describes what the tariff and the joint filing say, never what that contract says.
- The PLL-18 floor is quoted verbatim. Its result for any named customer depends on that customer's contract minimum and total contract capacity, neither of which is on the public record.
- The 1,605 MW figure is my multiplication of a printed capacity by a printed percentage, on a stated hypothetical. It is not a bill, a forecast or a company figure.
- The retrieved TOU-SC-16 copy is the Original schedule effective with bills rendered for June 2026. Whether a later revision changes the term or termination language was not established.
- The retrieved tariff book's cover page shows January 2023 with inserted revision pages; whether its pagination matches the book in force in November 2026 was not established.
- The Joint Statement is styled a joint statement by Commission Staff and the Company. Whether the Commission adopted it as an order was not established, and no part of this article depends on that question.
- The Incremental Cost Revenue Deficiency is defined across all large-load data center customers together, and its stated reductions are named without values. It is reported as a portfolio definition, not as any customer's exit price.
- Two accounts of the filing sequence are printed and neither is adopted: the fact sheet says contracts go to the Commission at least 30 days before execution, while the record for the seventh contract shows submission on 27 July 2026 and deemed approval on 26 August 2026.
- The news release's phrase "from 5-year contracts to 15-year contracts" is quoted as a press description. No tariff schedule in the set prints a fifteen-year term.
- The one-year default contract term and its thirty-day notice belong to the general rules; they are not the term or the notice of any large-load contract.
- Riders referenced by both schedules were not inspected, so no statement is made about a rider's effect on a minimum monthly bill.
- Quoted sentences appear inside quotation marks; descriptive statements about Section D and about the schedules' applicability and measurement clauses are summarised rather than quoted.
Member Briefing
Read the full trend briefing
Members read the full briefing with the source notes behind every finding.
Strategic Circle