Summary
- At 30 September 2026 Digital Realty reported $2.5 billion of annualised GAAP base rent from leases signed but not yet commenced at 100 per cent share, and $1.8 billion at its own share. The earnings presentation's schedule puts $1,846 million at share into three buckets: roughly $371 million before the year ends, $831 million in 2027 and $643 million in 2028 or later.
- The weighted-average lag between leases signed in the quarter and their contractual commencement date was 17 months. In the same quarter the company capitalised $70.964 million of interest into buildings under construction, which is 76.1 per cent of the $93.273 million of GAAP interest expense it reported — my division on two printed lines.
Two dates, one square metre
A data centre lease is signed long before it pays. The tenant commits to space that may not exist yet, the landlord starts buying steel, generators, switchgear and the power connection, and for a stretch of quarters the revenue line shows nothing from that commitment while the borrowing that funds it does not wait. Digital Realty's own earnings release calls the accumulated total what it is: signed but not commenced. At quarter end it stood at $2.5 billion of annualised GAAP base rent at 100 per cent share, and $1.8 billion at Digital Realty's share.
The release also dates the gap. The weighted-average lag between new leases signed during the third quarter of 2026 and their contractual commencement date was 17 months. Seventeen months is not a delay; it is the construction calendar of a building sold before it is finished, written as a single number.
The schedule, bucket by bucket
The earnings presentation goes further than the level, and this is where the disclosure earns its place. At Digital Realty's share the $1,846 million splits into approximately $371 million scheduled to commence in the balance of 2026, $831 million in 2027 and $643 million in 2028 or later. Divided by the total, those buckets are 20.1, 45.0 and 34.8 per cent of the backlog — my division, and consistent with the approximately 20, 45 and 35 per cent the presentation prints beside its own bars.
The same series appears at a second consolidation basis. The consolidated figure of $1,229 million splits into approximately $324 million for 2026, $665 million for 2027 and $241 million for 2028 or later. Those three buckets add to $1,230 million against the rounded $1,229 million — my addition, and a one-million rounding difference the presentation itself disclaims.
Two more printed quantities belong beside the schedule. The company states that backlog equals about 40 per cent of in-place Data Center Rent at Digital Realty's share, and that $207 million of annualised GAAP rent commenced during the third quarter. Set the two against each other and the near-term test appears: the $371 million bucket for the remainder of 2026 is roughly 1.8 times what converted in the quarter just ended, on two rounded printed figures.
What the footnote fixes
The presentation does not leave the measure floating. It defines the amounts as GAAP annualised base rent from leases signed but not yet commenced, based on estimated future commencement dates at the time of signing, and states that actual commencement dates may vary. Historical backlog, the footnote adds, is adjusted for asset sales and purchases, joint venture and fund contributions and other non-material reconciling items. That footnote is the whole discipline of the number. The dates are the company's estimates made at signature, and the series is rewritten when the portfolio changes shape.
The interest that waits in the building
The other half of the mechanism is the cost side, and it is printed in the financial supplement. Capitalised interest was $70.964 million in the third quarter of 2026, against $32.923 million in the third quarter of 2025, and $143.703 million for the nine months to 30 September 2026. The same supplement reports total GAAP interest expense of $93.273 million for the quarter.
Put the two lines together and 76.1 per cent of the quarter's GAAP interest expense was capitalised rather than expensed — my division. The year-on-year move in the capitalised line is a multiplication of 2.16 times $32.923 million, also my arithmetic. There is nothing hidden in this. Capitalising interest during construction is the standard treatment: the carrying cost sits on the balance sheet until the asset is placed in service, and the income statement sees it later, through depreciation. The useful consequence for a reader is narrower and more practical.
The interest expense a quarter reports is not the cash cost of the buildings that quarter is paying for, and the capitalised line is the measure of the difference.
The development table in the same supplement sizes the book that difference refers to. It shows 1,464 MW under construction and 63 per cent leased at 30 September 2026, with total expected development investment of $21,992.465 million at 100 per cent share and $15,291.176 million at Digital Realty's share, at an 11.6 per cent average expected stabilised yield. Current development investment of $6,370.495 million plus future investment of $15,621.970 million equals that $21,992.465 million exactly — my addition on two printed lines.
Multiply 1,464 MW by the printed 63 per cent and about 922 MW of the pipeline is already leased; that is my multiplication, not a printed figure, and it is the physical counterpart of the backlog schedule.
A printed pair that does not reconcile
There is one gap worth naming precisely, because it sits between the two documents that carry the number. The earnings release prints the backlog as $2.5 billion at 100 per cent share. The presentation's commencement series prints a consolidated figure of $1,229 million alongside $1,846 million at Digital Realty's share. No document read for this piece reconciles the release's 100-per-cent figure with the presentation's consolidated figure, and nothing here resolves them. Each is exact at its own document; the gap between them stays open.
What the schedule lets you test
Before this quarter, the honest way to describe Digital Realty's contracted-but-unbilled rent was as a level, and a level cannot be audited. A reader either believed it would convert or did not. The commencement schedule changes the terms of that argument. It says, in the company's own numbers, that only about a fifth of the at-share backlog was due to start before the end of 2026, while roughly 45 per cent sat in 2027 and 35 per cent in 2028 or later.
Anyone who wants to check the claim now has a dated bucket to check it against: the $371 million balance-of-2026 slice, measured against the $207 million that actually commenced in the third quarter.
Commencement dates are estimates made at signing, and the presentation says so. No document read for this piece quantifies how far past schedule earlier estimates have run, so the observation here is the schedule itself and the capitalised cost standing behind it — not a verdict on whether the company hits its dates. Digital Realty Trust, Inc. published all three documents on 29 October 2026; the figures above come from them. Sources: https://investor.digitalrealty.com/news-releases/news-release-details/digital-realty-reports-third-quarter-2026-results, https://investor.digitalrealty.com/static-files/dbe7bde5-da83-4211-8f76-0f7624c48eab, https://investor.digitalrealty.com/static-files/3314eea6-08dd-4a03-a8c5-bd2419b5d449. The company's directory entry is at https://btw.media/en/directory/digital-realty.
Member Briefing
Read the full trend briefing
Members read the full briefing with the source notes behind every finding.
Strategic Circle
A daily briefing in your language, built from changes we have verified.
Join for USD 20/monthCancel anytime.
Members also get the full research library, a daily briefing on the networks they follow and the private forum.