• Nscale and Microsoft signed a letter of intent for 1.35 GW of AI compute and around 430,000 NVIDIA Vera Rubin GPUs at the planned Monarch campus.
  • The 2 GW generator order and 8 GW site potential are separate power figures; permits, construction, delivery and commissioning remain outstanding.

The announcement combines three unfinished transactions

On 16 March 2026 Nscale announced an agreement to acquire American Intelligence & Power Corporation, including the Monarch Compute Campus in Mason County, and a letter of intent with Microsoft. Aker's market notice said AIPCorp held rights to acquire land at the site and put the Microsoft scope at roughly 430,000 NVIDIA Vera Rubin GPUs.

Those are not the same commitment. The acquisition governs corporate and site control; the Microsoft LOI describes prospective compute demand; NVIDIA supplies the Vera Rubin architecture; Caterpillar and Boyd CAT supply the power equipment. None of the releases shows 430,000 installed GPUs, customer acceptance or a live Microsoft service.

1.35 GW, 2 GW and 8 GW measure different things

The 1.35 GW figure is the planned AI-compute capacity covered by the Microsoft LOI. Nscale said deployment would arrive in multiple tranches beginning in late 2027. Its campus page now targets delivery of Phase 1 by early 2028, so the figure cannot be treated as current operating capacity.

The 2 GW figure concerns on-site power. Caterpillar said AIPCorp ordered 2 GW of fast-response natural-gas generator sets, backed by battery storage, with equipment deliveries scheduled from September 2026 through August 2027. Nscale later targeted 2 GW of generation by the first half of 2028. The 8 GW number is a longer-term site potential or expansion ambition, not installed generation or compute.

Permitting shows movement, not completion

The West Virginia Department of Environmental Protection lists air-construction permit application R14-0042 for Monarch Cloud Campus at Point Pleasant, received on 20 April 2026. That is evidence of an active permitting process, not an issued construction permit, a completed building or operational compute.

HB 2014 created the state framework for certified microgrids and high-impact data centres and says certification may apply regardless of development or operating stage. It also removes wide areas of county and municipal zoning, noise, lighting, land-use and permitting control. The certification is a governance status, not an uptime certificate.

Energy and community claims still need operating data

Monarch is designed around behind-the-meter natural-gas generation rather than a normal utility-grid supply. Nscale says the campus will not raise local electricity rates, will use closed-loop cooling without municipal drinking water and may later export power to the grid. It also says it is pursuing carbon sequestration. These are project claims and design intentions, not measured results.

West Virginia Public Broadcasting reported expected employment of more than 2,800 workers and local training plans, while also noting community concerns about noise and environmental effects. Contracts awarded, people hired, emissions, water use, noise and rate effects should be measured after permits, construction and operation rather than credited at announcement.

What to watch

  • Conversion of the Microsoft LOI into final service and lease contracts.
  • Closing and site-control disclosures for the AIPCorp transaction.
  • Disposition and conditions of WVDEP permit application R14-0042.
  • Generator deliveries, battery integration and commissioned power by 2027 and 2028.
  • Delivered Vera Rubin systems, installed GPU count and accepted compute capacity.
  • Measured emissions, sequestration, water, noise, grid exports, jobs and tax receipts.