Summary
- The Central Statistics Office reports that data centres used 6,969 GWh of metered electricity in 2024, 22 per cent of a total of 31,903 GWh, a share assembled by examining roughly 2.5 million meters to decide which meter points are data centres.
- EirGrid and SONI put peak data-centre demand at approximately 800 MW, and EirGrid's adequacy assessment contracts about 2,100 MVA at transmission plus 300 MVA at 110 kV distribution for a category that bundles data centres with other new technology loads.
- The gate that decides which connections proceed runs on maximum import capacity at a connection — a 1 MVA de minimis, a 10 MVA trigger — and no document in the reviewed set prints the row that would join a meter point to a capacity.
An average that looks like a peak
Take the CSO's 6,969 GWh for 2024 and divide by that year's 8,784 hours — 2024 was a leap year. The answer is 793.4 MW as an annual average. That is my arithmetic, not the agency's, and it is the reason this article exists.
Set it beside the figure EirGrid and SONI print: "The peak data centre demand to date is approximately 800 MW; approximately 650 MW connected on the transmission system and 150 MW on the distribution system" (EirGrid and SONI, November 2025).
An average landing within one per cent of a peak is not a coincidence to wave through. Buildings whose average equals their peak would be running flat out at full demand every hour of the year, Christmas morning included. Either the two figures describe different sets of connections, or one of them is not a metered peak, or the method absorbs the difference somewhere I cannot see. Nothing in the reviewed documents settles it, and I am not going to pretend otherwise.
EirGrid and SONI do print one warning that matters more than the arithmetic. For that paper they use megawatts rather than megavolt-amperes "for simplicity", and "The MW values referenced may differ slightly from their MVA equivalents which tend to be used in connection agreements and capacity statements" (same paper). Two of the three numbers in this story are not in the same unit as the third, and the operator says so before anyone asks.
Three percentages, one load
The CSO's figure is the most precise. Metered consumption by data centres rose 10 per cent from 6,335 GWh in 2023 to 6,969 GWh in 2024, and the share of metered electricity used by data centres rose to 22 per cent from 5 per cent in 2015. The Statistician's Comment describes that as data centres' share of total metered electricity consumption (CSO, 10 June 2025). Table 1 supplies the parts: 6,969 GWh for data centres, 24,934 GWh for other metered customers, 31,903 GWh in total. The components add up, and 6,969 over 31,903 is 21.85 per cent, rounded to 22.
The CRU calls the same 22 per cent something else. Its release announcing the connection decision describes demand "growing from 5% of national electricity demand in 2015 to 22% in 2024" (CRU). National electricity demand is not total metered electricity consumption, and the regulator, not the statistician, chose that phrase.
EirGrid and SONI supply the third: "Data centres and new technology loads comprised approximately 24% of Ireland's electrical energy requirements in 2024" (same paper). Read the category — data centres and new technology loads — and read the denominator — Ireland's electrical energy requirements.
Three phrases, three perimeters, three years of political argument resting on them. None is wrong on its own terms. None can be swapped for another without changing what a reader thinks is being measured.
How a meter point becomes a data centre
The CSO does not hide its method. Data centres, it says, "were not readily identifiable in the meter data so the CSO examined around 2.5 million meters to identify Meter Point Reference Numbers (MPRNs) that were considered as primarily being used for data centre activity" (CSO background notes). It lists four approaches: the type of business activity of large energy users; a search for names and aliases of known data centres above half a gigawatt hour; customers in specific business parks above half a gigawatt hour; and every meter above one gigawatt hour a year, supplemented by other organisations' reports, the CSO Business Register and internet searches. And it prints its own limit in seven words: "There is no agreed definition of a data centre."
Then comes the sentence that ought to be quoted in every summary of the 22 per cent. Revisions, the CSO explains, may arise from adding MPRNs or removing ones incorrectly included, because "A new data centre may have a relatively low amount of electricity consumption at first and hence may initially be below the search thresholds used to subset the 2.5 million electricity meters" (same notes). A facility joins the count when it grows large enough to be noticed. That is a defensible way to build an estimate, and it is also a selection rule with a threshold, published plainly, in a document almost nobody reads.
The same notes record that "A small number of data centres accounted for most of the metered electricity consumption by data centres" — concentration that makes the aggregate robust and still names nothing. In the inspected text there is no count of meter points and no count of facilities.
The fourth quantity
The instrument that decides which of these buildings may connect does not use GWh, MW or a percentage. It uses maximum import capacity at a connection.
CRU/2025236, published on 12 December 2025, sets a de-minimis level of 1 MVA; requires data centres at or above 10 MVA to provide dispatchable onsite or proximate generation or storage matching their MIC, subject to derating, separately connected and metered and participating in the wholesale electricity market; requires anyone at or above the de-minimis level to meet at least 80 per cent of annual demand from additional renewable electricity generated in the Republic of Ireland, on a six-year glide path from energisation; requires the system operators to weigh whether a connection and its generation sit in a constrained or unconstrained part of the network; and states that where an operator is not satisfied against the assessment criteria, "the application will not be processed by the SO, accordingly, the application will terminate" (CRU/2025236).
Every threshold in that paragraph is a capacity at a connection. The published statistics are an annual energy total and an operational demand over a fleet. There is no published conversion between the two, and no reviewed document so much as attempts one.
What the gate prints, and what it does not
On 20 May 2026 EirGrid published Data Centre Connection Offer Process and Policy Version 3 (DCCOPP Version 3). It applies to new transmission applications of 1 MVA or more received on or after 12 December 2025, and it prints nine numbered assessment criteria: 2.1 Generation Adequacy, 2.2 Renewable Electricity Requirements, 2.3 Constrained Area Assessment, 2.4 Dispatchable Onsite or Proximate Generation and/or Storage Capacity, 2.5 System Stability, 2.6 Capacity Market, 2.7 De-rating Factors, 2.8 Performance and Availability Requirements, 2.9 Planning Permission.
The consequence is printed too: "If EirGrid determines that an application does not meet these criteria, the application will not proceed and will be terminated." After termination, "a customer may not submit a new application for the same project until a minimum of six (6) months after the termination of the previous application." And the document concedes its own provisional status in a paragraph that names the Commission for Regulation of Utilities, the decision paper and its reference, and then names nothing else: no party, no case number, no filing date, no hearing date, no stay, no determination.
That is a great deal of published rule. What it is not is a published record of what the rule decided. In the inspected text there is no count of applications received, offered, refused, terminated or granted, and no list naming a connection with its maximum import capacity.
The distribution side does the same at its own voltage. ESB Networks routes a data centre applicant through both a demand and a generator form, NC3 and NC5, under the ECP-GSS process with batch closing deadlines currently 31 March and 30 September each year, notes that each application is assessed separately on a case-by-case basis, and reserves the right to terminate an agreement where an applicant does not stipulate that the facility is a data centre (ESB Networks). No tally of outcomes in the inspected text there either.
What the operator counts instead
The 2024 delivery record is a record of completions. "During 2024, two projects which facilitate demand connections totalling over 48 MVA were energised and/or completed" (EirGrid, Investment Planning and Delivery Report 2024), repeated in section 10.1.4 as two demand customer connections totalling over 48 MVA MIC. The same report counts 22 projects energised against a target of 29 and 43 Project Agreements, of which 24 were customer connection projects.
The adequacy assessment counts contracts and projects: approximately 2,100 MVA contracted at transmission and a further 300 MVA at 110 kV distribution, a 2024 demand of 959 MVA in a table captioned for the bundled category, and 17 transmission projects plus five at 110 kV that are connected or hold a signed agreement (EirGrid, AIRAA 2026–2035).
Every one of those is a delivery count or a contracted capacity. Not one is a count of applications disposed of. A reader can learn how much capacity arrived and cannot learn how many projects were turned away to get there.
What it took to learn three dates
EirGrid's 2025 freedom-of-information log carries the evidence in its plainest form. Request FOI_2025_016, received 20 June 2025 and decided on 2 July 2025, asked for the dates of the most recent, second most recent and third most recent accepted grid connection offers for a data centre on the transmission system. The decision recorded is "Granted" (FOI Disclosure Log 2025). A second request, FOI_2025_003, received 28 January 2025, asked for each connected data centre's name, its connection date and its monthly billed consumption to the fourth quarter of 2024, plus hourly load profiles for the year; it is recorded as withdrawn.
The log is a table of rows and, in the inspected text, contains no sentence of narrative policy. What it demonstrates without narrating anything is the route. Three dates required a formal request, and the row that would have produced the client list never reached a decision at all.
The row that does not exist
The article you have just read is not an accusation against a statistician or an operator. The CSO prints its search breadth, its thresholds, its definitional caveat and its revision rule. EirGrid prints its unit warning, its nine criteria, its termination consequence and a litigation notice. The CRU prints the thresholds the whole argument turns on.
What none of them prints is the join. The statistical agency counts meter points. The gate counts maximum import capacity. One row — facility, meter point, capacity granted, date of connection — would let a stranger take the 22 per cent apart, test whether the buildings contributing to it are the ones that crossed 10 MVA, and check whether the average and the peak are the same fleet. The 2025 freedom of information route shows the row exists inside the organisations. It has never been published as a row.
EirGrid, the transmission system operator, is the entity at the centre of this: EirGrid in the BTW directory.
Across the ten documents reviewed on 19 November 2026 — the CSO key findings and background notes, the EirGrid and SONI information paper of November 2025, EirGrid's adequacy assessment for 2026 to 2035, CRU/2025236, the CRU's own release on that decision, DCCOPP Version 3, the ESB Networks large energy user process, the 2025 freedom-of-information log and the 2024 delivery report — none prints a per-connection record joining a meter point to a maximum import capacity, and none prints a count of data centre applications received, granted, refused or terminated.
Several of those documents were read as extracted renderings rather than opened end to end, so that finding is bounded to the text inspected and to that date.
This article also adds something to what BTW has already published here. A briefing on this object dated 13 November 2026 read the offer mechanics: that planning permission delivers no megawatts, that the CRU writes its thresholds in megavolt-amperes, that EirGrid runs the gate and that the first to accept an offer wins the place when two applications collide. That is the instrument at the point of decision. This is the accounting around it — three denominators, a fourth unit, and the evidence that the operator publishes what it delivered rather than what it refused.
So publish the row, or publish the tally. Either would let an outsider do the one thing the current record forbids: count the refusals. Nine printed criteria and no printed verdicts ask the public to trust a number that the institution has decided, perhaps reasonably, not to say out loud.
Member Briefing
Read the full trend briefing
Members read the full briefing with the source notes behind every finding.
Strategic Circle
A daily briefing in your language, built from changes we have verified.
Join for USD 20/monthCancel anytime.
Members also get the full research library, a daily briefing on the networks they follow and the private forum.