Summary

  • RIPE Policy Proposal 2026-03 is still in “Discussion Phase: Awaiting decision” on 25 November 2026. The current-proposal index dates the discussion from 19 October through 17 November.
  • The proposal says it only clarifies the IPv6 post-provisioning framework. Its redline removes the ripe-738 paragraph that promises automatic licence renewal for holders making a good-faith effort. It also adds section 9, “Audit,” and section 10, “Closing an LIR by the RIPE NCC.”
  • The new closure section names three triggers: unpaid money owed to RIPE NCC, a significant period without contact, and consistent violation of RIPE community policies. It also says RIPE NCC takes responsibility for address space held by closing LIRs.
  • RIPE NCC Audit Activity explains that failure to supply requested audit information may lead to agreement termination. Non-cooperation or incorrect information can end in termination and possible deregistration. A holder can use the Conflict Arbitration Procedure.
  • The public proposal contains no vote, acceptance, withdrawal, implementation date or holder-level audit case. Those are the records that would turn the redline into an operating rule.

Eight days after the clock stopped, no verdict

The proposal page is neat enough to hide the pause. Publication date: 19 October. Version 1.0: 19 October. Discussion began the same day. The current-proposals index says discussion ended on 17 November. Eight days later, the state remains “Awaiting decision.”

RIPE NCC has therefore published the clock and the destination but not the result. The proposal was written by Marco Schmidt of RIPE NCC, affects ripe-738 and carries an indefinite policy term. Its route from a document edit to enforceable policy still has an empty final cell.

That gap matters because the issue is not a decorative spell check. IPv6 allocations live under a policy that calls the grant a licence, renews it periodically and reserves registry power over renewal. The proposal changes which lifecycle machinery appears inside that licence document.

“Clarification” is doing a lot of work

The summary says the goal is to make existing lifecycle requirements explicit and align the text with IPv4 policy. The rationale says it “aims strictly to clarify the existing framework, without making substantive changes to the original intent.”

Then the redline adds two sections that the current public ripe-738 page does not contain. Section 9 points to RIPE NCC’s audit activity. Section 10 lists conditions under which RIPE NCC may close an LIR and says RIPE NCC takes responsibility for the address space left behind.

The first two are titled “Audit” and “Closing an LIR by the RIPE NCC.” Calling the words clearer is fair. Calling the resulting policy surface identical is harder to defend. The IPv6 document would now tell a reader where audit procedure lives and how the holder’s registry relationship can end.

The old text’s renewal sentence is also struck from the redline. Current ripe-738 says RIRs generally renew licences automatically where the holder makes a good-faith effort, while bad faith can permit non-renewal. The proposed replacement omits that sentence and moves to audit and closure.

The proposal does not invent the audit procedure from thin air. RIPE-694 has existed since 2018 and already describes agreement termination and arbitration. The proposal’s job is to pull that procedure into the IPv6 policy’s own lifecycle story. That is editorial alignment with operational teeth.

The three closure triggers need sharper edges

The proposed section names unpaid money, prolonged uncontactability and consistent policy violation. One trigger has a bill attached. The other two rely on adjectives.

“Significant period” has no number in the proposed text. “Consistently violates” has no count, observation window, evidence standard or review sequence. The closure clause does not carry its own notice period, cure period, emergency exception or appeal term. RIPE-694 supplies an audit process and arbitration route, but the IPv6 policy only provides a pointer.

The audit document is more explicit. RIPE NCC can begin an Assisted Registry Check, a selected audit or a reported audit. It can decide whether to keep the review narrow or broaden it. It sets document deadlines. Failure to supply requested material may lead to termination. Incorrect or fraudulent information can also bring termination and deregistration.

Those are serious consequences with a separate procedure. They are exactly why the decision facing the community matters. A reader needs the join between section 10 and RIPE-694: which trigger, which evidence, which notice, which cure, which decision-maker and which arbitration clock.

Three fields still control the asset

An IPv6 allocation is not useful because a line of policy calls it a licence. It is useful because operators, customers, routes, reverse-DNS zones, security material and contracts depend on the same assignment. The registry controls the public record around that dependency.

That makes the representation of closure important. “RIPE NCC takes on responsibility for address space held by closing LIRs” is one sentence. It does not say whether space is frozen, reassigned, transferred, held for dispute, restored after arbitration or deregistered. The operational fate of live networks remains elsewhere.

The policy’s licence language makes the control visible. The audit language supplies a route to investigate. The closure language supplies a route to the registry exit. A serious administrative framework should make those three stages auditable as stages, with the exact event that moves a holder from one to the next.

Proposal 2026-03 is currently a map of that route. It still needs a decision before anyone can drive it.

Sources: proposal 2026-03; current policy proposals; ripe-738; RIPE NCC Audit Activity.