Summary

  • CoreWeave's Form 10-Q for the quarter ended 30 September 2026 prints $47.4 billion of undiscounted payments on leases not yet commenced, and names megawatts in that note only where power is still undelivered: 453 MW at a single site under a $16.9 billion rent cap, and 354 MW at other sites carrying no dollar figure at all.
  • Three filings price the same GPU shell from $100 to about $194 per kilowatt-month, and no reviewed page states whether the kilowatt being priced is the same unit as the megawatt being counted.

The number that never meets its unit

On 12 November 2026, CoreWeave, Inc filed its quarterly report for the period ended 30 September 2026, and the EDGAR record dates the filing accordingly (EDGAR filing detail, accession 0001769628-26-000465). Note 8 of that report gives the tenant side of the artificial-intelligence land grab in one paragraph: executed leases not yet commenced carry $47.4 billion of estimated future undiscounted payments, they commence between 2026 and 2029, and their estimated terms run seven to seventeen years (Form 10-Q, 30 September 2026).

Megawatts appear twice in that note, and both times they describe power that is not there. At a single site intended as a data centre, 453 MW of electrical power remained undelivered, expected in phases in 2026 and 2028, with rent based on construction costs incurred by the lessor and subject to a contractual maximum of $16.9 billion over the sixteen-year term. A further group of construction-cost-based leases had 354 MW undelivered, with payments during construction variable and contingent and no dollar amount included in the $47.4 billion estimate.

Read the note for capacity and you find a company that counts in megawatts only where it is waiting for them.

What the tenant counts

The annual report supplies the vocabulary the rest of the sector uses. CoreWeave's 2025 annual report reports 43 data centres with more than 850 MW of active power at 31 December 2025, against 32 data centres and approximately 360 MW a year earlier and 10 data centres and approximately 70 MW in 2023. Total contracted power capacity was approximately 3.1 GW, to be deployed over future periods, alongside $60.7 billion of remaining performance obligations and a weighted-average committed contract duration of about five years.

Nothing on those pages says whether an active megawatt is critical IT load or gross facility power. That single omission is what makes every price below incomparable, because the landlords quote their rent per kilowatt of contracted demand and the tenant quotes its footprint in megawatts whose boundary has not been drawn.

The landlord who prints the price

Core Scientific is the one counterparty in the reviewed record that puts a number on the unit. Its supplemental information of 21 April 2026 states that CoreWeave pays a base licence fee of $100 per kW per month, or $115 per kW per month at the Austin campus, with annual rent increases of 3.5 per cent and 3.0 per cent built into the agreements, over six data-centre facilities across five sites supporting approximately 590 MW of net critical IT capacity, with initial terms of twelve years except Austin's seven and CoreWeave paying all utility costs (Core Scientific, Exhibit 99.2, 21 April 2026).

The same document lists the allocations: 30 MW at Dalton 1, 145 MW at Dalton 4, 65 MW at Marble, 70 MW at Muskogee, 262 MW at Denton and 16.5 MW at Austin, which sum to 588.5 MW against the stated approximately 590 MW.

Arithmetic on a printed rate is legitimate, so do it. At $100 per kW per month a megawatt costs $100,000 a month and $1,200,000 a year. Compounded at the printed 3.5 per cent, the base fees on one megawatt over twelve years sum to about $17.5 million, and the twelfth-year rate is 51.1 per cent above the first. Austin is the exception that teaches the lesson: $115 per kW per month at 3.0 per cent over seven years totals roughly $10.6 million per megawatt. The higher rate on the shorter term is the smaller cheque.

The landlord who prints the formula and blanks the number

Applied Digital chose the opposite disclosure. Its 8-K of 2 June 2025 records two leases signed on 28 May 2025 by APLD ELN-02 LLC and APLD ELN-03 LLC, delivering up to an aggregate 250 MW at its 400 MW Ellendale, North Dakota campus — Building 2 at 100 MW, Building 3 at 150 MW — each on an initial term of approximately fifteen years followed by three five-year extension options, with expected total contract values over the initial term of approximately $3 billion and approximately $4 billion. CoreWeave may terminate on delivery failures by specified dates, and may terminate at any time on notice plus a specified termination fee (Applied Digital, Form 8-K of 2 June 2025).

The lease exhibit hands over the mechanism and withholds the price. The initial rate of Base Rent is [] per kW contracted for by the tenant per Data Hall per month, subject to annual escalation on each Escalation Date by [], against an Electricity Demand Threshold of 25,000 kW in each of four phases, with consumed utilities payable as Additional Rent (Building 2 lease exhibit, 28 May 2025). The contract defines the unit precisely — a kilowatt of contracted demand per hall, per month — and then declines to say what one costs.

The landlord's own schedule reassembles a price from the other end. Applied Digital's lessor note for the year ended 31 May 2025 reports $6,764,199 thousand of minimum contracted payments from the two CoreWeave leases, running from $81,156 thousand in fiscal 2026 to $394,793 thousand in fiscal 2030 and $5,206,486 thousand thereafter, excluding reimbursed operating expenses and variable rent increases (Applied Digital lessor schedule, fiscal 2025).

Two arithmetics follow, and they do not agree, which is the point. Spread the whole $6,764,199 thousand over 250 MW and a fifteen-year initial term and you get $1,803,786 per MW a year, or about $150 per kilowatt-month. Take instead the fiscal 2030 line of $394,793 thousand over the same 250 MW and you get $1,579,172 per MW a year, or about $132 per kilowatt-month — and that line has already absorbed escalations from each hall's commencement, so the starting rate sits below it. A redaction plus a schedule yields a range of about 14 per cent, not a rate.

The two expected contract values in the 8-K sum to approximately $7 billion against the schedule's $6,764,199 thousand, a difference of about $236 million, or 3.4 per cent, which the schedule's stated exclusions account for.

The only place the tenant prices a megawatt itself

Go back to the $16.9 billion cap and divide. Over the 453 MW still undelivered at that site, the cap is $37,307,947 per MW; across the sixteen-year term it is $2,331,747 per MW a year, or about $194 per kilowatt-month. That is a ceiling, built on a maximum tied to a lessor's construction spend, and the construction cost behind it is not printed. It is nonetheless the only place in the tenant's own filing where a megawatt and a dollar amount stand in the same paragraph.

The ladder, and the missing conversion

Put the three conventions on one surface and the spread is hard to miss. A licensed shell at Core Scientific is $100 per kilowatt-month at contract start. A leased shell at Applied Digital is somewhere near $132 to $150 per kilowatt-month, recovered from a schedule after the contract blanked the rate. The capped construction-cost site in CoreWeave's own note tops out near $194. The band between the low and high figures is 1.94 times.

None of those numbers can be used without the definition that is missing. Core Scientific alone qualifies its figure as net critical IT capacity; the other two do not, and no reviewed page prints a conversion between critical IT load and gross facility power. A megawatt priced at $100 on one boundary and $194 on another may be the same asset at two prices or two assets at one price, and the documents read do not settle which.

The scale of the commitment is available even if the rate is not. Executed undiscounted payments at 30 September 2026 — $32,954 million of commenced operating leases, $822 million of finance leases and $47.4 billion not yet commenced — total about $81.2 billion. Against the 3.1 GW reported nine months earlier, that is about $26 million per megawatt. Two dates and three asset classes sit inside that quotient, so it is a scale rather than a price; it still tells a reader that the obligation dwarfs any single campus.

What one quarter did

The prior quarterly note, for the period ended 30 June 2026, prints the same structure one quarter earlier: $35.5 billion of payments on leases not yet commenced, 393 MW undelivered at the capped site, a $14.7 billion cap, 355 MW in the unquantified group, and commenced operating lease payments of $29,135 million less imputed interest of $12,816 million for a present value of $16,319 million (Form 10-Q, 30 June 2026, Note 8).

Between the two filings, uncommenced payments rose $11.9 billion, the capped site gained 60 MW of undelivered power, its cap rose $2.2 billion, and undiscounted commenced payments rose $3,819 million. Operating lease liabilities went from $8,195 million at 31 December 2025 to $18,697 million at 30 September 2026, a factor of 2.28 in three quarters.

That is a company buying buildings faster than it can energise them, on contracts whose unit is printed by the seller, in a definition the buyer has not published. The megawatt, not the dollar, is where this business is levered; it is also the only term in the structure that nobody has defined.