Summary
- Three submarine cables faulted in the Red Sea on one day, Saturday 24 February 2024: AAE-1, EIG and SEACOM. Some accounts reported four, because SEACOM and Tata TGN-Eurasia are one cable under two names.
- The committee that keeps the industry's repair file prints the same annual count six ways and the cause split at four different percentages, and states plainly that it owns neither the routes nor the fault records.
- Across the 25 documents read on 25 November 2026, the only published faults-per-kilometre figure covers fishing and anchor damage in water shallower than 1,000 metres and stops in 2018.
- The corridor's own clock ran 73 days to permits for two of three cables, 144 days to the first cable back online and 150 days to the statement that all three were finished — of which the repair ship spent 16 days working.
On Saturday 24 February 2024, three submarine cables in the Red Sea were reported to have faulted on the same day. TeleGeography named them: AAE-1, EIG and SEACOM/Tata TGN-Eurasia. Some accounts counted four, which is one of the cleaner counting errors in this story, because SEACOM and Tata TGN-Eurasia are two names for one cable. A Bloomberg report republished by Insurance Journal treats it the same way, and the Center for Strategic and International Studies prints the third system as Seacom/TGN-Gulf and the disruption as roughly a quarter of all Asia-to-Europe traffic. Three renderings of one cable, in three documents, about one fault.
Four days after the faults, the International Cable Protection Committee issued a statement about the Red Sea. It named none of the damaged systems. It printed more than 400 cable systems, 1.5 million kilometres and, quoted exactly, "on average around 150 faults occur each year, which are mostly due to accidental human activities such as fishing and anchoring." Every one of those figures is global. The custodian of the industry's fault file, writing about the corridor in the week it happened, published no corridor figure at all.
Then there is the count itself, and the number of ways the same custodian prints it. Its public FAQ says approximately 150–200 faults occur globally each year. A 2025 viewpoint repeats the 150–200 and says fishing and anchoring cause more than 70 percent. A co-authored ITU article says around 200, with over 80 per cent from fishing and anchoring. The 2026 plenary highlights say 178 repairs took place in 2025 against a stated 190 annual average, and do not say which years that average covers. The 2025 plenary highlights say 204 reported repairs in 2024, almost unchanged from 201 in 2023. Trade coverage of the same analysis says 199 faults a year on average from 2010 to 2024, and separately 206 repairs in 2023. The ITU backgrounder says over 170 repairs in 2025, almost four a week.
Six figures for one quantity, from one file, most of them on pages the same organisation controls. They are not wildly apart — 150 to 204 is roughly a third, and a third is the difference between a good year and a bad one. The point is that the band moves without a published definition of what it counts, and two of the three averages carry no period at all.
The cause split moves further. It is 70–80 percent in the FAQ and the viewpoint, over 80 percent in the ITU piece, and 86 percent in the plenary and trade coverage. The statistical analysis breaks the same file down as fishing 28 per cent, anchoring 14 per cent and a further 38 per cent undecided between the two. Then a 2025 ICPC post prints dragged anchors alone at nearly 30 per cent of incidents worldwide, around 60 faults a year. Anchoring is 14 per cent in the table and nearly 30 per cent in the post; the two pages are not stated to cover the same period, so they sit side by side rather than averaged. The same organisation's 2009 bulletin explains why such numbers move: once AIS tracking was applied, anchor damage from vessels underway turned out to have been undercounted, and the UK split went from fishing 67 per cent and anchors 8 per cent to fishing 33 per cent and anchors 48 per cent. The count changed because the instrument changed.
The length has the same problem. The FAQ says telecommunications cable grew from 1 million kilometres in 2014 to approximately 1.7 million in 2025. TeleGeography says over 1.5 million kilometres in service as of early 2026, counting in-service cable and excluding planned and decommissioned systems. The SubOptic coverage says route mileage rose from 1.5 million to 2.7 million kilometres. Systems are variously more than 400, about 450, 500-plus and more than 600. A November 2024 Business Wire piece prints 450 systems and more than 1.5 million kilometres without stating what length means.
Divide the year's count by each of the three lengths and the same 178 repairs become 0.119, 0.105 and 0.066 faults per 1,000 kilometres per year — a spread of 1.8 times, produced entirely by the choice of denominator. That quotient is mine, not the industry's, and it is here to show what definitional drift is worth. It is worth more than a year's variation.
The duration is better behaved, and still carries two starting points. The 2025 plenary prints 22.5 days between notification and departure plus 6.5 days transit for 2024. The 2026 plenary prints 23.4 and 7.7 days for 2025. The statistical analysis prints 22.5 days from fault to ship sailing plus 7.5 days transit, says contemporary averages approach 50 days against two to three weeks in 2012, and records a longest delay of 947 days. Both the plenary and the analysis print that 947 days.
It is 2.6 years, and roughly 30 times the 31.1-day mean the plenary prints for the same year — mine again, and the one quotient this record genuinely begs for.
And the rate? The one per-kilometre series in the ICPC corpus covers fishing and anchor faults in water shallower than 1,000 metres: about 0.2 faults per 1,000 kilometres in 2010, about 0.05 by 2018, cited to Kordahi and others, 2019. A depth band, a cause pair, a secondary citation, no year-by-year table. The fault file's published geography is the maritime zone — 2 per cent high seas, 55 per cent exclusive economic zone, 43 per cent territorial waters in 2024 — plus one country, where China averaged a fault every 12 days. No named sea.
And the file is not public. The FAQ says the committee "does not own or share cable route or fault data, which is confidential to cable owners." The analysis describes a database of more than 3,000 repair records drawn from Cable Maintenance Agreements, with coordinates and cable names withheld. The publisher of the count holds neither the count nor the map. It holds a tally of what members reported, and it prints that tally as the world's.
Which leaves the corridor. TeleGeography counted 14 cables already laid in the Red Sea and 11 remaining after the three faults; Insurance Journal attributes the same 14 in-service plus six planned. The 2025 ICPC post counts 15 in-service cables through Bab el-Mandeb — later, differently bounded, and not a contradiction so much as two footprints wearing one name. Neither page prints a kilometre total for the corridor. So the day three of 14 cables failed was a single day on which about 21 per cent of the corridor's systems were hit, and 1.7 per cent of the world's 2025 repairs — both mine — and nobody can say whether that day was extraordinary, because there is no corridor denominator and no corridor history.
What the corridor does have is a clock, and its printed endpoints are worth reading in order, counted from the fault date. On 7 May 2024 the Yemeni government granted permits for two of the three cables and refused the third over a dispute with a consortium member: 73 days. On 15 May repairs to AAE-1 were being held during a criminal investigation of the cable owners' alleged ties to the Houthi militia, with about 20 telecoms in the consortium targeted and TeleYemen among them. The vessel's mission began on 8 July. On 17 July AAE-1, a 25,000-kilometre system, came back online and the same ship stayed on for the other two: 144 days, and nine of them after the ship sailed. On 23–24 July the Sana'a ministries announced completion for all three, crediting the Maritime Affairs Authority in Sana'a with the facilitation and permits, a claim Data Center Dynamics reported from the same statement and an industry observer: 150 days, of which the ship worked 16.
Compare that with the sentence the ITU–ICPC advisory body published in July 2026: a pan-African provider reported in March 2024 that approvals for its damaged Red Sea cable "could take up to 8 weeks — repairs that were subsequently completed in July 2024." Eight weeks is 56 days. The permits for two of the three cables were printed 73 days after the fault, seventeen days beyond the stated bound, and the repairs finished in July 2024 as the report says. The passage does not name the permitting state. EnterpriseAM moves the same eight weeks to Egypt; neither the Sana'a statement nor the ITU sentence puts these permits there, so the attribution stays with the outlet that made it.
BTW has been here twice already, both on 12 November 2026: "The Red Sea's Cables Are Redundant. Its Permits Aren't." counted the coastal states' instruments and found no restoration deadline among them, and "The Red Sea's Cables Wait on a Signature, Not a Ship" set the two July 2024 accounts of that repair beside each other and showed a ship's completion and a permit's existence need not coincide. Three earlier pieces — September 2025 twice, July 2024 once — reported the cuts and their traffic effects as events.
None of the five asked how many faults the corridor records, in what unit, over what window, or what the repair clock reads when its endpoints are printed instead of assumed. That is the question here, and the permission argument is left where they put it.
The falsifiable test is one sentence: if the count comes from the repair-file custodian, the length from a commercial mapping house on its own schedule and the duration from the custodian's plenary slide, then no reader can form a Red Sea fault rate from any of the three, because the corridor has no published kilometre figure and the year has no published corridor count.
So publish the corridor. One page, four fields, one period and one definition: faults in the Red Sea corridor this year; kilometres of cable in the Red Sea corridor this year; days from fault to permit and fault to restoration; and the quotient of the first two. The Red Sea cable corridor is a place name standing in for a population of cable-kilometres that nobody counts as a population — and the industry's own stability claim, that faults hold flat while the network grows, is a claim about a rate that no one has printed for the water where the faults happen.
Member Briefing
Read the full trend briefing
Members read the full briefing with the source notes behind every finding.
Strategic Circle