Summary
- Rate Schedule GS-5's filed text defines a High Load Customer by original contracted demand, or maximum measured demand, of 25 MW or more in at least three of the current and previous eleven billing months, with demand measured as the highest average kW in any 30-minute interval.
- Dominion's own PJM filings report a data-centre billing peak of 4.8 GW as of August 2026 and a 2046 coincident demand of 18,890 MW, then put a floor on charges at a percentage of the kVA capacity of the facilities required to serve the load; no reviewed document prints the power factor that joins the two.
The order says megawatts, the tariff says kVA
Case No. PUR-2025-00058 is Dominion's 2025 biennial review under Va. Code § 56-585.1 A. The application went in on 31 March 2025, the Final Order issued on 25 November 2025, and the Commission's own release that day carried the same date. What the order says about its new class is one sentence. Final Order in Case No. PUR-2025-00058
The GS-5 rate class shall include customers with: (1) a measured or contracted demand of 25 megawatts (“MW”) or greater on a contiguous site; and (2) a measured or expected load factor of at least 75%.
Measured or contracted demand, in megawatts, on a contiguous site, plus a 75 per cent load factor. The Commission repeated that formulation in a later order on 30 June 2026 and cited it to page 23 of the biennial order, so the two-part test is a finding, not only a proposal. Order of 30 June 2026
The instrument that actually bills the class was filed ten and a half months later, received 5 October 2026 and accepted 14 October 2026, and it keeps the 25 MW line while rebuilding everything underneath it:
the Company's (i) original contracted demand is equal to or exceeds 25 MW, or (ii) maximum measured demand is equal to or exceeds 25 MW, with such usage occurring for at least three billing months, of the current and previous eleven billing months.
Section XXVII, Rate Schedule GS-5 High Load/High Load Factor Service
The same sheets supply the three items the order never prints. Demand is the highest average kW in any 30-minute interval. The actual monthly load factor is monthly kWh divided by days in the billing month, divided by 24, divided by maximum measured kW demand. And a measured-demand customer qualifies by repeating the test in three of eleven billing months — an interval, a formula and a clock that no other reviewed document carries.
Then the unit changes. The order set collateral at $1.5 million per MW; the filed tariff states $1.5 million per MVA of contracted capacity. The order approved minimum demand charges of 85 per cent of contracted demand for distribution, 85 per cent for transmission and 60 per cent for generation; the tariff states 85 and 60 per cent of the kVA capacity of normal facilities required to serve projected load. Where a customer contracts 25 MW and the required facilities are rated at exactly 25 MVA, the two bases coincide. Where the facilities are rated above the contracted megawatts, the percentage is taken on the larger number.
That is my arithmetic, and it stops there: no reviewed document prints the power factor that converts one base into the other, so this article computes no dollar amount from either rate.
The reach of the tariff is wider than its class. Section XXVII applies to accounts served under Schedules 6, 6TS, 10, GS-3, GS-4, GS-5, MBR or SCR — the high-load terms follow the 25 MW customer onto schedules it may not otherwise occupy. The legacy 500 kW line on Schedule GS-4 is still there for everyone else, and from 1 January 2027 a high-load demand determination applies to a non-residential customer at 25 MW or more who does not qualify for GS-5. Schedule GS-4 tariff sheets
One sentence for the press, three for the docket
The sentence most readers will meet first is shorter than all of this. The Commission's release of 25 November 2025 says “the Commission said the new GS-5 rate class will comprise customers demanding 25 megawatts or more”, effective 1 January 2027 — no measurement basis, no interval, no load-factor test. Commission news release The staff fact sheet of February 2026 keeps the shape and drops the numbers: “Large load customers, such as hyperscale data centers, were placed into a new separate rate class, the “GS-5 rate class.”” SCC Data Center Initiatives fact sheet
The name travels badly too. A consultant whitepaper of May 2026 calls the class the “Very Large General Service Rate (GS-5)”, a phrase the filed instrument never uses; the schedule's own title is High Load/High Load Factor Service. E3 large load tariff whitepaper
‘Not a data center class’, 131 of 139
Dominion's filed testimony summary is the most quoted and least read document here. Stan Blackwell, Director of the Data Center Practice, states that the criteria captured 139 existing accounts, of which 131 were data centres and eight were not, and that GS-5 “is not a data center class”. Direct testimony summary of Stan Blackwell
Both halves hold at once. My division puts data centres at about 94.2 per cent of the accounts captured. A class that is 94.2 per cent data centres by account count is not thereby defined by data centres — and it is worth saying plainly that the sentence is a witness's, not a Commission finding.
The opt-out legislation shows the same distinction from the other side. Six customers elected under 2026 Va. Acts ch. 1124 to stay on GS-4 instead of moving to GS-5 for revenue apportionment, and the election is limited to customers with at least 200 manufacturing, industrial or warehousing full-time equivalent employees as of 1 January 2026, excluding data storage. Order granting motion, 3 September 2026 Excluding data storage does not exempt a data centre; it makes one ineligible. The Final Order otherwise remains in force.
The half Dominion publishes to PJM
Now the other side of the pair. Dominion's 6 January 2026 data-center large-load adjustment to PJM asks for coincident-peak values and says the Company “currently serves the largest data center market in the world with a 2025 coincident peak of 4 GW” — Dominion's sentence, in Dominion's filing, with the number attached. The next line is the one to keep:
The Company is forecasting 16.6 GW of demand by 2046, not the 47 GW of capacity. This difference highlights the difference between capacity and demand.
Dominion data center large load adjustment, 6 January 2026
By September the numbers had moved and the machinery had become visible. The presentation to PJM's Load Analysis Subcommittee states that “Data center billing peak load as of August 2026 is 4.8 GW”, forecasts 2027 coincident demand of 5,075 MW rising to 18,890 MW in 2046 and 19,466 MW in 2047, and prints a separate capacity row of 11,590 MW in 2027 and 34,299 MW in 2046 and 2047. Its contract book reads 9,356 MW of firm Construction Letters of Authorization, 11,997 MW of firm Electric Service Agreements and 32,473 MW of Engineering Letters of Authorization, with 13,429 MW of ELOA inside the forecast and 19,044 MW excluded. Dominion LSE 20-year data center forecast, 29 September 2026
Add the contract book up and it comes to 53,826 MW — my sum, not a printed total. The method matters more than the total: the deck models billing demand from connected and contracted load, applies a utilisation rate and energisation timing, and then calculates coincident demand from billing demand using a historical coincident/billing-demand ratio. Dominion therefore does compute a billing quantity. It then converts that quantity into a PJM number for a different purpose, and that is the last place in the filing where billing demand appears.
Rackline, a trade publication, reports the January table's exact cells as 4,433 MW in 2026 rising to 16,636 MW in 2046, and about 53.8 GW of contracted capacity as of July 2026, including 12.0 GW of ESA, 9.4 GW of CLOA and 32.4 GW of ELOA. Those figures are Rackline's reading of the documents, not cells I could see; the January letter's own table cells were not visible in the copy I read. Rackline, 20 October 2026
The two vintages are eight months apart and 2,290 MW apart at 2046 — 16.6 GW in January against 18,890 MW in September, my subtraction, a change of vintage for PJM's 2027 forecast cycle rather than a correction.
The plan names the class and stops at the meter
The 2026 Integrated Resource Plan Update, filed 15 October 2026 in Case No. PUR-2026-00163, is where a reader would expect the join. It presents DOM Zone coincident peak in MW and annual energy in GWh for 2026 through 2046, and it defines the quantity precisely: coincident peak is “the demand on the DOM Zone system that occurs during the PJM RTO peak”, as against non-coincident peak, “which would be the peak demand for the LSE”. Dominion 2026 Integrated Resource Plan Update
It also names GS-5, describes the class as contracted or measured demand of at least 25 MW with an anticipated or measured load factor of 75 per cent or more from 1 January 2027, and says data centres generally fit that profile without the class being exclusive to them. What it does not do, on the pages I read, is connect the forecast megawatt to the billing quantity. Additions to the data-center forecast are named as a key driver of year-over-year change, and the methodology and underlying data sit in Appendix 4A and Appendix 4B, neither of which I read.
That is an absence over a named document on a named date, not a claim that the link does not exist.
What would join them
One number would close most of it: the power factor at which the customer's kilowatts become the facilities' kilovolt-amperes, printed beside the minimum demand charge. A second would close the rest: one worked example taking a forecast year, a single account's maximum measured demand in a billing month, and the resulting minimum charge on the same page.
Neither is in the twelve documents I read on 24 November 2026. What is in them is a definition that is unusually complete — an interval, a qualifying period, a load-factor formula — and two published quantities that never meet it. The seller prices the object in the kVA of its own equipment. The seller's forecast reports it as a coincident peak for a different buyer. Between those two sentences sits a building, a meter and a 30-minute interval, and the invoice.
That the reviewed documents stop where they stop is a fact about twelve printings, not about the utility. Nothing here says any rate is unlawful or excessive, that anyone has been overcharged, or that anything was withheld. The final order was read from a mirror hosted by VPM rather than the Commission's own docket copy, so its page numbers — including the page 23 the June order cites — are unverified against the stamped original. The tariff pages are a scan with visible optical-recognition defects, so some punctuation and figures were not checked against the stamped sheets. Neither PJM document names GS-5 in the text I saw.
The 139 and 131 counts are Dominion's, from a filing whose date is not printed on the retrieved page. And because no reviewed document prints a power factor, this article never converts kVA to kW or MW to MVA, and never multiplies a megawatt figure by the per-MVA rate.
The twelve documents: the Final Order in Case No. PUR-2025-00058; the compliance filing and revised Section XXVII tariff sheets; the Commission's news release of 25 November 2025; the Direct Testimony Summary of Stan Blackwell; the Schedule GS-4 tariff sheets with their 2027 redlines; the Commission's order of 30 June 2026; the order granting motion of 3 September 2026; Dominion's data center large load adjustment to PJM of 6 January 2026; the LSE 20-year data center forecast of 29 September 2026; the 2026 Integrated Resource Plan Update; Rackline's 20 October 2026 analysis; and the E3 large load tariff whitepaper of May 2026.
Member Briefing
Read the full trend briefing
Members read the full briefing with the source notes behind every finding.
Strategic Circle
A daily briefing in your language, built from changes we have verified.
Join for USD 20/monthCancel anytime.
Members also get the full research library, a daily briefing on the networks they follow and the private forum.