Summary
- At 30 June, 590 MW was leased to CoreWeave and 395 MW was billable; the remaining 195 MW sat in construction and commissioning.
- By mid-July, 437 MW was billing. After new AMD and neocloud agreements, total leased capacity reached roughly 1.1 GW and more than US$24 billion of potential contracted revenue.
- About US$1.0 billion of purchase and construction commitments, 7.75% secured debt and rent-start conditions sit between leased power and collected cash.
A megawatt changes meaning as it moves through the campus
A megawatt is not a megawatt. On a utility interconnection agreement it is a promise; at the substation it is a number stamped on a transformer nameplate; at the customer rack it is a meter reading that finally starts the clock on rent. Core Scientific spent the second quarter living in the gap between those definitions — and by mid-July that gap was roughly 660 megawatts wide.
The company's pivot from bitcoin mining to high-density colocation is now big enough to be measured in several power ledgers at once, and the ledgers do not agree. At 30 June, Core Scientific controlled about 2.1 GW of gross utility power and estimated 1.3 GW of total leasable customer power across 11 US data centres. Those figures describe the physical and engineering perimeter, including capacity nobody has signed for yet.
The contractual perimeter was narrower. CoreWeave had leased about 590 MW across five sites. Only 395 MW had commenced billing at quarter-end, leaving 195 MW still crawling through construction and commissioning. Billing capacity had climbed fast — from 120 MW in fiscal Q4 2025 to 225 MW in Q1 and 395 MW in Q2 — but leased capacity kept running ahead of the revenue-producing base.
Then, on 28 July, Core Scientific announced 15-year agreements with AMD and a neocloud tenant for roughly 530 MW. Stacked on the CoreWeave estate, the company described about 1.1 GW of leased customer capacity and more than US$24 billion of potential contracted revenue. By mid-July, however, just 437 MW was actually billing, representing about US$635 million of average annualised colocation GAAP revenue.
Keep the dates and definitions apart. The 1.1 GW reflects agreements announced after quarter-end. The 437 MW is a mid-July operating measure. Potential contracted revenue stretches across long terms and depends on delivery; it is not current revenue, not cash, and not a one-year backlog. The AMD relationship may expand toward 2.5 GW, but expansion potential is neither leased nor billable capacity.
The conversion chain is physical before it is financial
A utility agreement does not energise a customer rack. Land, interconnection, substations, transformers, switchgear, cooling, fibre, halls and customer-specific fit-out have to arrive in sequence — and every link can slip. Systems must be commissioned and accepted. Only then does the relevant rent or licence start, and only then does billing become possible.
That sequence showed up in current results. Q2 colocation revenue reached US$136.7 million, up from US$10.6 million a year earlier, as more billable MW entered service. Total quarterly revenue was US$164.2 million. The improvement is proof the conversion mechanism works; it does not close the remaining construction gap.
At 30 June, Core Scientific was contractually committed to about US$1.0 billion of future purchase and construction expenditure, substantially all expected within 12 months. US$264 million would be passed through to a customer as invoiced. The filing does not allocate every remaining dollar to the 195 MW CoreWeave gap, later AMD sites or development for prospective customers, so the residual cannot be labelled a disclosed cost of one capacity cohort.
Financing follows delivery milestones, but it does not erase them
Core Scientific Finance issued US$3.3 billion of 7.75% senior secured notes due 2031. The secured project entities own or operate specified developments. The first instalment date is tied to rent commencement and the end of revenue credits under related data-centre leases — a design that wires amortisation timing to operating delivery.
It does not make timing costless. Revenue credits reduce the tenant's payment obligation during ramp-up. Construction commitments still require labour, equipment and deposits. A delayed hall can postpone billing while interest and project overhead keep running. Customer concentration matters too: CoreWeave remained the primary obligor after certain licences were assigned into a special-purpose financing structure.
The useful market dashboard therefore has several rows: gross utility MW, leasable MW, leased MW, construction MW, commissioned MW, billing MW, revenue per billing MW, unspent commitments, customer pass-throughs, credits, debt service and collected cash. Collapsing them into "power capacity" turns an execution chain into a promotional total.
Sources
Member Briefing
Read the full trend briefing
Members read the full briefing with the source notes behind every finding.
Strategic Circle
A daily briefing in your language, built from changes we have verified.
Join for USD 20/monthCancel anytime.
Members also get the full research library, a daily briefing on the networks they follow and the private forum.






