- Bylaws Article 4.6 runs the Accountability and Transparency review, the Security, Stability and Resiliency review and the Registration Directory Service review "no less frequently than every five years" measured from the date the previous review team was convened. The CCT review alone hangs on a different trigger: one year after a new gTLD round begins operating.
- On 3 May 2026 the Board approved Resolution 2026.05.03.09, adding a new Section 27.6 to Article 27 without touching the text of Article 4.6. That section suspends all four reviews and prints its own ceiling, extension test and restart ladder.
- The effective date is not a calendar day. It is the completion of the Empowered Community process. The Empowered Community Administration certified on 9 June 2026 that the rejection procedure had terminated, and the current Bylaws page now carries a 3 July 2026 header.
The three clocks the Bylaws print
The sentence in Article 4.6 puts the measuring point before the number. The Accountability and Transparency provision reads: "The Accountability and Transparency Review shall be conducted no less frequently than every five years measured from the date the previous Accountability and Transparency Review Team was convened." Five years is the interval; the anchor is the convening of the previous team. I read that sentence in the consolidated text published 9 January 2025, ICANN Bylaws, 9 January 2025 text.
The Security, Stability and Resiliency provision uses the same formula. So does the Registration Directory Service provision, which keeps the "no less frequently than every five years" wording and adds a one-time bridge: the first review after 1 October 2016 counts as timely if its team is convened by 31 October of that year. What the three sentences share is not the interval but the method. The anchor sits on an external event — the convening of a review team — rather than on an internal decision of the institution being reviewed.
The fourth review is built differently. Article 4.6(d), which covers the Competition, Consumer Trust and Consumer Choice review, does not put that review on the five-year cycle at all. It ties the review to a condition: one year after a new gTLD round begins operating. The hypothesis we carried into reservation — that the 2018 CCT final report started one of these four clocks — does not survive that sentence.
This article therefore limits the five-year claim to the Accountability and Transparency, Security, Stability and Resiliency, and Registration Directory Service reviews, and treats the CCT review as a fourth review that was never on that cycle to begin with.
May 2026: the resolution that stops the clock
On 3 May 2026 the Board approved a Standard Bylaws Amendment adding a new transition article to Article 27. The resolution reads: "Resolved (2026.05.03.09), the ICANN Board approves the addition of a new Transition Article to the ICANN Bylaws, to be inserted at Article 27, Section 27.6 of the ICANN Bylaws, pursuant to the Standard Bylaws Amendment process set forth at Article 25, Section 25.1 of the ICANN Bylaws." The same page records that the amendment began on 25 January 2026 and that public comment ran from 11 February to 13 April 2026. The resolution and its rationale are published as Board resolution, 3 May 2026.
Three things in the rationale deserve attention. First, it states that the amendment leaves the text of Article 4.6 untouched. Second, the Board records its own history: it deferred the start of the next Accountability and Transparency review in 2024 and again in 2025, and the third cycles of the Security, Stability and Resiliency review and the Registration Directory Service review had also slipped past the Bylaws' starting point. Third, ALAC asked for the pause to be counted from September 2025 rather than from the amendment's approval date, and the Board says it did not move that point.
What matters here is not that a pause exists but that the pause was written down. An institution that prints its own deferrals makes the dates of those decisions auditable. Had the pause lived only in scheduling practice, nobody could later count it.
What the text of the article prints
The approved transition article carries two status lines at once: "APPROVED BY ICANN BOARD – 3 May 2026" and "Subject to Empowered Community Process." The text creates Section 27.6 under the heading "Timing for Specific Reviews" and defines the effective date not as a calendar day but as the completion of the Empowered Community process. The document is published as Transition Article text, approved 3 May 2026.
From that effective date, the obligation to conduct the four reviews in Article 4.6(b) through (e) is suspended. The pause is 12 months by default and cannot exceed 24. Extension has two doors. The Board may accept and direct implementation of community recommendations issued after the effective date, or four of the seven supporting organisations and advisory committees may state that they support a further pause. Either way, a rationale has to follow.
Restart is not a return to the five-year cycle. It is a ladder. The Accountability and Transparency review begins within 90 days; the Security, Stability and Resiliency review begins within 18 months of that review's start; the Registration Directory Service review begins within 18 months of the Security, Stability and Resiliency review's start, with an alternative that keys the timing to the preceding final report.
The CCT review's restart is fixed to the 2026 round's delegation numbers: two years after the first 500 applied-for gTLDs are delegated if applications reach 2,000 or more, or two years after 25 percent of applied-for gTLDs are delegated if they do not. And Section 27.6 says that an amendment to Article 4.6 during the pause replaces the transition article.
One note on the form of the document. This PDF reached this record as table-shaped text extracted by a search adapter; some section numbers are disordered and no page was compared against a rendered image. The phrases quoted are as printed in the extracted text.
The May letter and the 9 June certification
Board approval alone does not create effect, and the correspondence shows it. The Secretary-General's notice of 11 May 2026 told the Empowered Community Administration and the Deciding Participants that the Board had approved the Article 27 amendment on 3 May, and framed their role as reviewing whether to reject that approval. The notice is published as Secretary-General notice, 11 May 2026.
A month later the review was over. On 9 June 2026 the Empowered Community Administration certified that the rejection procedure for the Article 27 Standard Bylaws Amendment "has been terminated." The reason is explicit: after ALAC's notice of a Community Rejection Action Petition on 1 June 2026, no other Deciding Participant's support arrived before the petition support window expired at 06:59 UTC on 9 June. The certification cites Annex D, Section 2.2(d)(ii). It is published as Empowered Community Administration certification, 9 June 2026.
The Address Supporting Organization published its own account of the path. It consulted the Regional Internet Registry community, received no supporting input, and decided that "the ASO will not support the Community Rejection Petition." That sentence, in the ASO follow-up notice, records in a participant's own words how the rejection procedure came apart.
What the fourth review actually left behind
The CCT review completed one full cycle inside this record. A Board resolution of 1 March 2019 records that the first CCT review team was announced on 23 December 2015, that it delivered a final report on 8 September 2018 containing 35 full consensus recommendations, and that the Board acted on those recommendations on 1 March 2019. That chronology is in the Board resolution of 1 March 2019.
The annual review implementation report counts the same events from a slightly different angle. It records that the CCT review team announced in December 2015 had 17 community representatives and subject matter experts, and that the final report arrived in September 2018 after almost three years of work. That sentence, in the Annual Review Implementation Report for 1 July 2019–30 June 2020, discloses the gap between convening and report on its own terms.
The Governmental Advisory Committee's March 2019 briefing calls the starting point something else. The first CCT review was "initiated on 23 December 2015," it says, and was conducted under the Affirmation of Commitments that the Bylaws replaced after the IANA stewardship transition of 1 October 2016. The GAC CCT review briefing, March 2019 carries that sentence. The Board resolution calls the same day an announcement; the GAC calls it an initiation. No document in this record reconciles the two words.
The review hub shows how the next CCT cycle was planned. ATRT3 Recommendation 3.2 put the CCT review "within the two years after the first introduction of the (possible) next round of new gTLDs to the root." That phrase, in the ICANN reviews hub, and the 2026 transition article's delegation thresholds define the same review's start by different events. One is the round's first introduction; the other is 500 delegations or 25 percent.
The current Bylaws page: a header, and a text I could not read
The consolidated Bylaws page carries "As amended 3 July 2026" in its header, publishes both the Article 27 transition article and the Article 4.6 specific review provisions, and still prints the Registration Directory Service review's "no less frequently than every five years" sentence. It is the current ICANN Bylaws.
Here the boundary of this record has to be stated plainly. That page was read only in the portions returned; the text of Section 27.6 and the sentences of Article 4.6(b) and (c) were not read directly on the current version. For those two provisions I rely on the 9 January 2025 text and on the Board's statement that the amendment left Article 4.6 untouched. I did not read the effective date in the article text either.
What this record does establish is that the Empowered Community's rejection procedure terminated on 9 June 2026, that the amendment defines the effective date as the completion of that procedure, and that the current page displays "As amended 3 July 2026."
The arithmetic that remains, and the gap that remains
What follows is my arithmetic. If the effective date falls on or after 9 June 2026, the 24-month ceiling cannot end before 9 June 2028. Applying the 12-month default pause from the same date, the obligation does not resume before June 2027 unless one of the two extension tests is met. Both figures are arithmetic on two printed provisions; they are dates I calculated, not dates the documents print.
There is also a calculation I did not make. No document in this record states the convening date of the third Accountability and Transparency review team. So this article does not compute how far the five-year cycle has slipped. The date 23 December 2015 is printed only as the CCT review's start; it is not the Accountability and Transparency review's anchor.
What remains is one structural question. Article 4.6 put the measuring point for three reviews outside the institution under review — on the convening of the previous team. The 2026 transition article stops all four and re-anchors the restart on two events the institution itself operates: the round's delegation count and the completion of the Empowered Community process. The ceiling disciplines the length of the pause. It does not discipline who picked the anchor. The institution's directory entry is at ICANN directory page.
Member Briefing
Read the full trend briefing
Members read the full briefing with the source notes behind every finding.
Strategic Circle
A daily briefing in your language, built from changes we have verified.
Join for USD 20/monthCancel anytime.
Members also get the full research library, a daily briefing on the networks they follow and the private forum.