The name was on page one
The name sits halfway down a single page of court order, between the recitals and the judge's signature: Gowtamsingh Dabee. Anyone who opened the document on AFRINIC's own website could have found it. For a while, this publication did not — and that omission, more than the name, is the instructive part.
That order is dated 12 February 2025. It replaces the Official Receiver with Dabee and gives the outgoing officer two weeks to hand over a report. The same page tells the newly appointed receiver to get on with electing AFRINIC's board. The appointment and the election were never two stories; they were one page.
An earlier version of this article built its argument around an unidentified supervisor and dated the appointment to May 2026. The record corrects both. What survives the correction is the more interesting question: if the receiver has been named and in place since February 2025, why is his exit still an open file?
A network cannot wait for an election
Within a month of the appointment, the receiver had a concrete problem on his desk. In a letter of 7 March 2025, ICANN's chief technology officer, John Crain, wrote to Dabee about restarting number-resource assignments. ICANN had received at least one formal complaint from an applicant who had waited months for a response or an assignment, and it urged AFRINIC to resume that work while the board election was being organised.
For an operator preparing to expand, those months are not administrative trivia. A resource application needs a decision; an election decides who governs the body that makes it. Crain wanted both jobs run in parallel. An applicant could hardly plan a network around the assurance that election preparations were progressing.
The complaint gives the wait a date. It also gives the story something a service catalogue cannot: an account, from outside the registry, of a request going unanswered.
A board returns; the receiver asks to leave
The September 2025 board election was itself a rerun. AFRINIC's receiver annulled the June 2025 election on 26 June 2025, and the rerun's rules barred the proxy voting that Article 12.12 of AFRINIC's constitution allows. Cloud Innovation does not recognise the board it produced (Cloud Innovation's answers).
Electing a board did not make the receiver disappear. A joint statement published on 13 October 2025 said Dabee had filed an application to terminate the receivership on 8 October, and described the board and receiver working together pending his formal discharge. The statement listed the work waiting for that board: the search for a chief executive, which it called a shared priority, and financial audits for 2022, 2023 and 2024, with the reports to be published once approved.
AFRINIC's published case index, checked on 25 October 2026, lists the discharge application under SC/COM/MOT/000757/2025 as awaiting judgment. In it the receiver also asks the Court to declare the September 2025 appointments valid. Cloud Innovation opposes that, because the election departed from AFRINIC's constitution and the Court's orders (what is still before the Court). No discharge order has been published. Dabee's role ends only when the Court decides — and the filing is already more than a year old.
Approvals resume, on AFRINIC's account
The registry reported progress on resource decisions in its member update of 12 March 2026. AFRINIC said the receiver was approving allocations and assignments that had completed the application process under prevailing policies. It also said Cloud Innovation Ltd was challenging his authority to do so in court.
That is AFRINIC's account of progress after Crain's appeal, and AFRINIC's description of the challenge. Cloud Innovation's stated aim is a registry that keeps running and is run lawfully: the winding-up it has asked the Court for is orderly, under the Court's supervision and with a successor registry, so that services continue (Cloud Innovation's answers). What AFRINIC has not published is a complete processing-time series showing how long applicants actually waited. A useful follow-up would put dates against applications, from submission through assessment to decision.
May's orders answered different questions
The earlier article also misread a date. AFRINIC's 15 May 2026 communiqué discussed court action the previous day; it did not announce the appointment of a receiver.
One published court instrument records an interim injunction restraining statements that the Court approved the leasing or commercialisation of AFRINIC-allocated IP resources. AFRINIC's communiqué calls such statements "false and misleading"; that is AFRINIC's wording, not a finding. The receiver obtained the injunction without notice to Cloud Innovation, over a press release published by LARUS Limited. Cloud Innovation's answer is that no one made the claim it restrains: a lawful business needs no court approval. It is an interim order, not a final judgment, and it decides nothing about whether leasing is lawful, who holds the addresses, Cloud Innovation's place in AFRINIC's register or LARUS's business (the interim order of 2026).
Another order dated 14 May allows ICANN to intervene in the winding-up proceedings brought by Cloud Innovation Ltd. Permission to intervene gives ICANN a part in that proceeding; it does not wind up AFRINIC. Dabee's appointment belongs to the February 2025 order, fifteen months earlier.
The next start date
On 24 August 2026, AFRINIC announced Mike Silber as CEO Designate, due to take office on 1 January 2027. The announcement said the board had acted with the receiver's consent and that both had initiated the search committee.
Silber's arrival is still ahead. The announcement records consent for this particular appointment; it says nothing about who authorises the next budget, contract or resource decision. Expanding one consent into a veto over everything would put more into the announcement than it contains.
The January start date gives members a leadership milestone to follow. An applicant whose plans depend on additional resources may need an answer sooner. Where has the application reached, and what decision is still required? A new chief executive, a discharged receiver and a completed application would each be a meaningful result. AFRINIC's members have reason to ask for the dates of all three.
Correction, 25 October 2026: the earlier version incorrectly placed the receiver's appointment on 14 May 2026 and said his identity and appointing instrument had not been publicly disclosed. The February 2025 order names Gowtamsingh Dabee; ICANN correspondence also identifies him. This version corrects the chronology and removes unsupported inferences about undisclosed authority and service continuity. The original URL and publication date are retained.
Correction, 14 November 2026: this version records that AFRINIC's receiver annulled the June 2025 election on 26 June 2025, attributes to AFRINIC its description of the interim order and of the legal challenge, and gives Cloud Innovation's answer beside them. This version also removes caveats that excused AFRINIC and its receiver. The original URL and publication date are retained.
Member Briefing
Read the full trend briefing
Members read the full briefing with the source notes behind every finding.
Strategic Circle