Summary

  • The CRTC wants to know how regional carriers have used wholesale mobile access: which customers they serve and which radio sites they have added. Responses are due 13 November 2026.
  • The access mandate expires on 9 May 2030. That deadline, not a CRTC investment quota, was the intended prod to build.

A mobile network can grow without a single new tower breaking the skyline. Bolt a regional carrier's radios onto an incumbent's existing mast, and for the CRTC's latest information request, that counts as expansion. It is the perfect way into a policy whose progress is far harder to photograph than a construction crane.

Canada's facilities-based MVNO framework lets eligible regional carriers ride incumbent networks into new territory while they build their own. Customers can sign up before a local network is finished — competition arrives early, at least on paper. It also leaves a blunt engineering question hanging: when the obligation to supply access expires, what actually carries those customers' calls?

The date is 9 May 2030. It marks the end of mandated supply, not an order to switch off every commercial deal or every handset. Still, it recasts today's wholesale arrangements as a lease with an expiry, not an indefinite entitlement.

What has happened since the agreement?

In its 13 October 2026 letter, CRTC staff asks Bell Mobility, Rogers, TELUS and SaskTel for their regional-carrier agreements, copies and start and expiry dates. Note the guest list: these are four incumbent hosts, not four national carriers — the framework treats SaskTel differently from the big three.

Cogeco, Eastlink, Iristel and Quebecor (acting for Videotron and Freedom) get the sharper questions. In every Tier 4 spectrum area where they lean on wholesale access to sell retail service, they must name their customers and list the new radio access network sites deployed since that use began. Kit bolted onto shared towers is expressly included.

The request then asks for total capital tied to expansion into those new areas — actual figures where readily available, otherwise the best estimate — plus the additional sites planned between the response and May 2030. It does not demand an audited investment figure for every area. Nor is a planned site a poured foundation.

Those distinctions matter. A customer count shows commercial use of access. A new radio site shows a physical addition. A spending total supplies another slice of the account, but it needs a period and a definition of what was counted. None substitutes for the others.

A deadline instead of a building quota

The choice was deliberate. In its 2021 policy, paragraphs 383–388, the CRTC weighed investment targets and declined to set them, worried about a number high enough to spur construction yet low enough not to sink smaller carriers. ISED's spectrum-licence build-out obligations were a separate lever; they did not vanish.

Instead, the CRTC leaned on a limited access window and annual progress updates. The final tariff order of 9 May 2023 starts the seven-year clock. The October letter is a consolidated look as that clock nears its halfway mark.

So a thin site count would raise a question about the policy's progress — not automatically prove a breached quota. And a fat count would not prove wholesale access caused every addition; some projects were already on the drawing board. The letter alone cannot supply that counterfactual, and the regulator has other reporting channels.

Fewer reports need not mean less information

That matters because a second CRTC process is running in parallel. The 6 October reporting consultation asks whether separate MVNO progress reports are still needed. Its stated reason is duplication: paragraph 17 says the information needed to track the framework is already gathered annually through the Data Collection System.

This is not an announced end to oversight. The consultation takes interventions until 20 November 2026 and replies until 22 January 2027. The separate information request has the earlier deadline: responses must reach the CRTC by 13 November, not merely be postmarked that day.

Abridged filings are required for the public record, with reasons for any confidentiality claim. That does not promise every financial figure will see daylight. It should, though, give the public a better shot at seeing how contracts, customers and construction fit together.

The test is not whether Canada can count more towers. It is whether a temporary way into a market is hardening into a durable way to compete in it. The October letter asks for evidence. It does not yet deliver the answer.

Updated 25 October 2026: this version corrects the description of the four host carriers and clarifies the investment figures requested, the absence of a CRTC investment quota and the reporting consultation's duplication rationale. The original URL and publication date are retained.